Calendario Inscripciones definitivas Montevideo

SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 1 de 9
Fecha de Impresión:
22/10/2014 8:04:32
OPERACIONES CON TORRES: 21/10/2014 06:00am AL 22/10/2014 06:00am
RIG:
POZO:
CCDC-069
AUCA-O068
EN COMPLETACION
ACAO-068
MD (Pies):
10,550
TVD (Pies):
10,177.1
PROD.ESTIMADA: (BPPD)
DETALLE:
ARMANDO TUBOXTUBO TUBING 3 1/2" EUE EN 6200'
RIG:
POZO:
H&P 121
PALO AZUL-N054
EN COMPLETACION
PALO AZUL-N054
MD (Pies):
10,520
TVD (Pies):
10,195.3
PROD.ESTIMADA: (BPPD)
DETALLE:
ARMANDO SISTEMAS DE BOMBAS (4)
RIG:
POZO:
H&P 132
EDEN YUTURI-D183
EDYD-183
MD (Pies):
8,774
TVD (Pies):
7,637.3
PROD.ESTIMADA: (BPPD)
DETALLE:
WOC
RIG:
POZO:
EN COMPLETACION
NABORS 815
YURALPA NORESTE-E102
YRNE-102
EN COMPLETACION
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
EVALUANDO ARENA HOLLÍN INTERVALO 8486' - 8498' (12 ft), CON BOMBA JET REVERSA 12 L
DETALLE:
CONVENCIONAL, CON MTU CIA. SERTECPET Y RIG NABORS 815. BFPD: 473, BSW: 88.4 %.
RIG:
POZO:
OCEAN SPUR
AMISTAD-015
EN COMPLETACION
AMS-015S1
MD (Pies):
10,696
TVD (Pies):
10,219.2
PROD.ESTIMADA: (BPPD)
DETALLE:
ARMANDO EQUIPO SLICK LINE
RIG:
POZO:
PDVSA-80
LAGO AGRIO-J052
EN COMPLETACION
LGAJ-052
MD (Pies):
10,650
TVD (Pies):
10,351.4
PROD.ESTIMADA: (BPPD)
DETALLE:
BAJANDO CONJUNTO TCP EN 3 1/2" EUE TUBING CLASE " A" CALIBRANDO @ 1400'
RIG:
PETREX 5824
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 2 de 9
Fecha de Impresión:
22/10/2014 8:04:32
POZO:
APAIKA-A012H
EN COMPLETACION
APKA-012H
MD (Pies):
10,518
TVD (Pies):
6,121.5
PROD.ESTIMADA: (BPPD)
FINALIZA EVENTO DE COMPLETACION DEL POZO APKA 12H EL DIA 21 DE OCTUBRE DEL 2014 A
DETALLE:
LAS 22:30 OK.
RIG:
POZO:
PETROTECH 04
YUCA-G034
EN COMPLETACION
YCAG-034
MD (Pies):
5,868.4
TVD (Pies):
5,429
PROD.ESTIMADA: (BPPD)
EVALUANDO ARENA "Tinf" CON ELEMTOS DE PRESION, JET 11J Y UNIDAD MTU: P. INY = 3500
DETALLE:
PSI. INY DIA = 2421
BSW INY = 98%. TBR = 603
BFPH = 10.4
BFPD = 250
BSWF = 23%. BSWR = 91 % SAL = 9000 PPM ¬CL
RIG:
POZO:
SINOPEC 191
OSO-I140
EN COMPLETACION
OSOI-140
MD (Pies):
9,500
TVD (Pies):
9,396.4
PROD.ESTIMADA: (BPPD)
DETALLE:
ARMANDO BHA C/SISTEMA HYDRAJET PERFORATING C/TBG D/3 1/2" A 35', SIN TERMINAR
RIG:
POZO:
CCDC-039
CUYABENO-C060
CYBC-060
EN MOVILIZACION
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
REALIZA REUNION DE SEGURIDAD PREVIO A CONTINUAR MOVILIZACION Y ARMADO DEL
DETALLE:
EQUIPO DEL RIG CCDC 39
RIG:
POZO:
PETREX 5824
APAIKA-A013H
APKA-013H
EN MOVILIZACION
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
PREPARANDO RIG DE PERFORACION PARA REALIZAR SKIDDING DESDE EL POZO APKA 12H AL
DETALLE:
POZO APKA 13H
RIG:
POZO:
CCDC-036
LIMONCOCHA-H060H
EN PERFORACION
LMNH-060R1
MD (Pies):
8,215
TVD (Pies):
7,919.9
PROD.ESTIMADA: (BPPD)
PERFORANDO ROTANDO HUECO DE 8-1/2" CON BHA No.3 CON PARAMETROS NORMALES @ 8215'
DETALLE:
EST
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 3 de 9
Fecha de Impresión:
22/10/2014 8:04:32
RIG:
POZO:
CCDC-038
ARAZA-A007
EN PERFORACION
ARAZA-A007
MD (Pies):
5,364
TVD (Pies):
5,405.2
PROD.ESTIMADA: (BPPD)
CIA. SAN ANTONIO QUIEBRA CABEZA DE CEMENTACIÓN 13 3/8" Y DESARMA LÍNEAS EN
DETALLE:
SUPERFICIE
RIG:
POZO:
CCDC-066
COCA-A054
EN PERFORACION
COCA-054
MD (Pies):
10,005
TVD (Pies):
8,959.8
PROD.ESTIMADA: (BPPD)
DETALLE:
SACANDO BHA # 4 DIRECCIONAL CON AUTOTRACK Y BROCA PDC 12 1/4" @ 3000 FT
RIG:
POZO:
CCDC-068
AUCA-K180
EN PERFORACION
ACAK-180
MD (Pies):
10,245
TVD (Pies):
9,559.3
PROD.ESTIMADA: (BPPD)
DETALLE:
BAJANDO CASING 9-5/8", N-80, 47#, BC @ 5700'.
RIG:
POZO:
NABORS 609
CHONTA SUR-A002
EN PERFORACION
CHSA-002
MD (Pies):
12,380
TVD (Pies):
10,546.6
PROD.ESTIMADA: (BPPD)
BAJANDO BHA # 9 DD @ 11000,BROCA PDC 8 1/2" + GVR / ECOSCOPEY TELESCOPE ( LWD +
DETALLE:
MWD )
RIG:
POZO:
NABORS 794
JIVINO-E020
EN PERFORACION
JVNE-020
MD (Pies):
6,342
TVD (Pies):
5,678.6
PROD.ESTIMADA: (BPPD)
DETALLE:
SACANDO BHA # 03 CONVENCIONAL C/ BROCA PDC 16" EN MODO BACK REAMING @ 5900'
RIG:
POZO:
PDVSA-81
LAGO AGRIO-H060
EN PERFORACION
LGAH-060
MD (Pies):
413
TVD (Pies):
413
PROD.ESTIMADA: (BPPD)
DETALLE:
GYRO DATA TOMANDO GYRO PREVIO A INICIAR KOP
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 4 de 9
Fecha de Impresión:
22/10/2014 8:04:32
RIG:
POZO:
SINOPEC 119
COCA-K044
EN PERFORACION
COCK-044
MD (Pies):
7,375
TVD (Pies):
6,101.8
PROD.ESTIMADA: (BPPD)
CIRCULANDO FONDOS ARRIBA + DENSIFICANDO SISTEMA DEL ACTIVO PREVIO A REALIZAR
DETALLE:
VIAJE CALIBRACION.
RIG:
POZO:
SINOPEC 127
OSO-H119
EN PERFORACION
OSOH-119
MD (Pies):
9,640
TVD (Pies):
9,459.9
PROD.ESTIMADA: (BPPD)
DETALLE:
CIRCULANDO A 9640 FT PARA LIMPIEZA DE POZO PREVIO A CEMENTACION
RIG:
POZO:
SINOPEC 128
AUCA-Q118
EN PERFORACION
ACAQ-118S1
MD (Pies):
10,735
TVD (Pies):
10,735
PROD.ESTIMADA: (BPPD)
DETALLE:
BAJANDO LINER DE 7" 26 #/PIE P-110 BTC @ 9000'.
RIG:
POZO:
SINOPEC 129
OSO-A150
EN PERFORACION
OSOA-150
MD (Pies):
10,864
TVD (Pies):
9,138.7
PROD.ESTIMADA: (BPPD)
PERFORANDO CON BHA # 13 DIRECCIONAL + MOTOR DE FONDO + BROCA PDC DE 8-1/2" @
DETALLE:
10864' MD.
RIG:
POZO:
SINOPEC 156
AUCA-P175
EN PERFORACION
ACAP-175
MD (Pies):
9,240
TVD (Pies):
7,677.5
PROD.ESTIMADA: (BPPD)
REALIZANDO VIAJE DE CALIBRE CON BHA # 4 EN HOYO ABIERTO DESDE 9240' HASTA 6380'
DETALLE:
ZAPATO, CORTAN 120' DE CABLE DE PERFORACION.
RIG:
POZO:
SINOPEC 168
OSO-G099
EN PERFORACION
OSOG-099
MD (Pies):
9,230
TVD (Pies):
8,947.9
PROD.ESTIMADA: (BPPD)
DETALLE:
PERFORA CON BROCA 12 1/4" Y MOTOR DE FDO. CON LWD/MWD/T. COMBO @ 9230 PIES.
RIG:
POZO:
SINOPEC 169
DRAGO NORTE-A042
DRRA-042
EN PERFORACION
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 5 de 9
Fecha de Impresión:
22/10/2014 8:04:32
MD (Pies):
5,878
TVD (Pies):
5,566.6
PROD.ESTIMADA: (BPPD)
DETALLE:
PERFORANDO SECCION 12 1 /4" CON BHA DIRECCIONAL # 4 Y BROCA PDC @ 5878 FT
RIG:
POZO:
SINOPEC 248
CONONACO-I040
EN PERFORACION
CNOI-040S1
MD (Pies):
8,933
TVD (Pies):
8,674.1
PROD.ESTIMADA: (BPPD)
DETALLE:
BAJANDO BHA#5 DIRECCIONAL CON 8-1/2" BROCA PDC A 8931 FT
RIG:
POZO:
HILONG 18
EDEN YUTURI-K107
EDYK-107
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
BAJANDO BHA DE PESCA EN 3-½" DRILL PIPE MIDIENDO CALIBRANDO Y SUBIENDO DE
DETALLE:
CABALLETES 1 X 1
A LAS 06:00 HRS DENTRO DEL POZO @ 791' CON 25 JOINT + BHA
RIG:
POZO:
CCDC-041
FRONTERA-006
FRN-006
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
DETALLE:
SACANDO COMPLETACION DE BOMBEO HIDRAULICO EN 3 1/2" EUE TUBERIA CLASE "B"
RIG:
POZO:
CCDC-052
ARMADILLO A 001
EN WORKOVER
ARMA-001
MD (Pies):
6,500
TVD (Pies):
6,500
PROD.ESTIMADA: (BPPD)
EVALUANDO ARENA "BT" CON BOMBA JET CLAW 11-K (PAM) Y UNIDAD MTU DE CIA. SERTECPET
DETALLE:
AL TANQUE BOTA DE FACILIDADES EN LA LOCACIÓN.
RIG:
POZO:
DYGOIL-30
SHUSHUFINDI-H202
SHSH-202
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
INSTALANDO 13 3/8" x 11" x 5000 PSI ADAPTER + 11" x 5000 PSI EXTENSIÓN + 11" x 5000 PSI
DETALLE:
BOP.
RIG:
POZO:
GEOPETSA-01
LAGO AGRIO-013
EN WORKOVER
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 6 de 9
Fecha de Impresión:
22/10/2014 8:04:32
LGA-013
MD (Pies):
3,201.5
TVD (Pies):
3,201.5
PROD.ESTIMADA: (BPPD)
DETALLE:
EVALUANDO ARENA "US" CON BOMBA JET MAS UNIDAD MTU DE CÍA. SERTECPET
RIG:
POZO:
GEOPETSA-06
LAGO AGRIO-E024
EN WORKOVER
LGAE-024
MD (Pies):
8,901.2
TVD (Pies):
8,901.2
PROD.ESTIMADA: (BPPD)
DETALLE:
EVALUANDO ARENA "B.T" CON BOMBA JET 9-I Y UNIDAD MTU AL TANQUE BOTA DEL RIG.
RIG:
POZO:
HILONG 28
PAKA NORTE-A010
EN WORKOVER
PKNA-010
MD (Pies):
11,169
TVD (Pies):
9,486.3
PROD.ESTIMADA: (BPPD)
CONTINUA EVALUACION DE LA ARENA U INFERIOR CON BOMBA JET CLAW DIRECTA 3 1/2" x
2.81" 12 K + UNIDAD MTU HACIA LA ESTACION: PRESION DE INYECCION 3500 PSI, 120 BBL
DETALLE:
INYECTADOS POR HORA, 39 BBL RECUPERADOS POR HORA, TOTAL 914 BBLS RECUPERADOS,
BSW = 95 %.
RIG:
POZO:
KEY 80051
SHUSHUFINDI-044
EN WORKOVER
SHS-044
MD (Pies):
7,300
TVD (Pies):
7,300
PROD.ESTIMADA: (BPPD)
A LA 06:00HRS BAJANDO BHA MOLEDOR EN 2-7/8" DP MIDIENDO Y CALIBRANDO CIRCULANDO
DETALLE:
CSG TBG CADA 2500 FT. DENTRO DEL POZO 6112 FT (191 JOINT) + BHA.
RIG:
POZO:
KEY 80057
SHUSHUFINDI-H015B
SHSH-015B
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
DETALLE:
DESARMA RIG-80057
RIG:
POZO:
KEY 80057
SHUSHUFINDI-S107
EN WORKOVER
SHSS-107
MD (Pies):
700
TVD (Pies):
700
PROD.ESTIMADA: (BPPD)
DETALLE:
ESPERA LUZ DEL DIA PARA DESARMAR RIG KEY-80057
RIG:
NABORS 813
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
POZO:
EDEN YUTURI-H149H
EDYH-149H
Página 7 de 9
Fecha de Impresión:
22/10/2014 8:04:32
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
SACANDO BHA # 07 DE PESCA CON 8 1/2" OVERSHOT EN 3 1/2'' DP EN PARADAS. 06H00 FUERA
DETALLE:
DEL POZO 4300' (68 PARADAS 3 1/2" DP)
RIG:
POZO:
NABORS 814
PALO AZUL-C040
EN WORKOVER
PLAC-040
MD (Pies):
0
TVD (Pies):
0
PROD.ESTIMADA: (BPPD)
DETALLE:
ARMAR EQUIPO SLICK LINE EQUIPETROL, PARA BAJAR CON 3-1/2" BLOQUE IMPRESOR.
RIG:
POZO:
NABORS 819
PAKA SUR-A005
PKSA-005
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
DETALLE:
RETIRANDO SUB ESTRUCTURA DEL RIG.
RIG:
POZO:
SAXON 32
OSO-A055H
EN WORKOVER
OSOA-055H
MD (Pies):
9,147
TVD (Pies):
8,576.9
PROD.ESTIMADA: (BPPD)
CIRCULANDO EN REVERSA PARA LIMPIEZA DEL POZO @ 9147' CON FLUIDO DE CONTROL DE 8.9
DETALLE:
LPG AL TANQUE DE LODOS.
RIG:
POZO:
SAXON 34
SECOYA-014
EN WORKOVER
SCY-014
MD (Pies):
3,300
TVD (Pies):
3,300
PROD.ESTIMADA: (BPPD)
BAJANDO BHA DE PESCA N° 2 EN 3 1/2" DRILL PIPE, MIDIENDO Y CALIBRANDO. DENTRO DEL
DETALLE:
POZO 3300FT.
RIG:
POZO:
SAXON 47
SECOYA-018
EN WORKOVER
SCY-018
MD (Pies):
9,207.8
TVD (Pies):
9,207.8
PROD.ESTIMADA: (BPPD)
BAJANDO BHA DE ASENTAMIENTO 7" CIBP EN 3-1/2" EUE TBG EN PARADAS;
MIDIENDO.,CALIBRANDO EN CADA PIN DE LOS TUBOS DESE 42,45' Y PROBANDO CON 3000 PSI
DETALLE:
CADA 24 PARADAS
DENTRO DEL POZO A LAS 06H00: 7379'
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 8 de 9
Fecha de Impresión:
22/10/2014 8:04:32
RIG:
POZO:
SAXON 55
PICHINCHA-007
EN WORKOVER
PCH-007
MD (Pies):
6,104.9
TVD (Pies):
6,104.9
PROD.ESTIMADA: (BPPD)
CONT. REALIZANDO PRUEBA DE "T CON BES BAKER CENTRILIFT PF10XH6 A LA ESTACIÓN
DETALLE:
PICHINCHA
RIG:
POZO:
TRIBOILGAS-008
DRAGO NORTE-C021
DRRC-021
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
SACANDO 3 1/2" TUBERIA EUE CLASE "B" CON CABLE ELÉCTRICO, QUEBRANDO A LOS
DETALLE:
CABALLETES, RETIRA PROTECTORES CANNON Y MID-JOINTS. FUERA DEL POZO 7500' A LAS
06H00
RIG:
POZO:
TRIBOILGAS-101
TIPISHCA-C014
TPSC-014
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
Bajando BHA de limpieza con 6 1/8" broca en tuberia 3-1/2" eue en paradas desde la torre
DETALLE:
midiendo.
A las 6:00 dentro del pozo 5200'
RIG:
POZO:
TRIBOILGAS-102
CONONACO-C046
CNOC-046R1
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
EVALUANDO ARENA “Us” CON BOMBA JET 12-K ( GEOMETRIA DE PAM): P.INY = 3500 PSI ; BIPH
DETALLE:
= 120 BLS. ; BSW INY. = 88% /// TBR= 380 BLS; BFPH = 14 BLS. ; BFPD = 336 BLS.; BSW
PRODUCCIÓN = 42%; SALINIDAD: 2000 PPMCL
RIG:
POZO:
TRIBOILGAS-103
ANACONDA-A008
EN WORKOVER
ANCA-008
MD (Pies):
10,645
TVD (Pies):
10,032.8
PROD.ESTIMADA: (BPPD)
DETALLE:
CAMBIANDO VALVULA LATERAL DE 2-1/16" x 5000 PSI SECCION "B"
RIG:
POZO:
TRIBOILGAS-104
AUCA-018
EN WORKOVER
ACA-018
SUMARIO DE OPERACIONES
PRODUCCION Y PERFORACION
Página 9 de 9
Fecha de Impresión:
22/10/2014 8:04:32
MD (Pies):
8,977
TVD (Pies):
8,977
PROD.ESTIMADA: (BPPD)
REALIZANDO PRUEBA DE PRODUCCIÓN DE EQUIPO BES P4X H6 A ARENA "BASAL TENA" AL
DETALLE:
TANQUE BOTA DEL RIG
RIG:
POZO:
TRIBOILGAS-107
VICTOR HUGO RUALES-003
VHR-003
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA: (BPPD)
TECNICO DE CIA SCHLUMBERGER REDA DESARMANDO EQUIPO BES: 3-1/2" DESCARGA EUE ,
DETALLE:
DESCARGA PHOENIX , BOMBA D800N , SEPARADOR DE GAS , 2 PROTECTORES
RIG:
POZO:
TRIBOILGAS-201
LAGO AGRIO-033
EN WORKOVER
LGA-033
MD (Pies):
247.5
TVD (Pies):
247.5
PROD.ESTIMADA: (BPPD)
ARMANDO BHA DE PESCA: 4 3/4" ARPON (SLB), 3 1/2" D.P (1), 4 3/4" SPEAR STOP, 4 3/4"
DETALLE:
MARTILLO HIDRAULICO, 4 3/4" DRILL COLLARS (6).
RIG:
POZO:
TUSCANY 108
PACAYACU-B009
PYAB-009
EN WORKOVER
MD (Pies):
TVD (Pies):
PROD.ESTIMADA:500 (BPPD)
SACANDO BHA DE EVALUACION CON TUBERIA DE 3 1/2" TSH BLUE EN PARADAS CON LLAVE DE
DETALLE:
TORQUE DE CIA ITS, LLENANDO EL POZO CADA 10 PARADAS FUERA DEL POZO A LAS 06:00 HRS
6300' CON 200 TUBOS
DESCRIPCION DE UNIDADES:
BPPD: Barriles de Petróleo por día