Gorgon Project Update Selected Images, January 30, 2015

Gorgon Project Update
January 30, 2015
© 2015 Chevron Corporation. All rights reserved.
Project Progress

Gorgon Project execution activities are now 90 percent complete.
© 2015 Chevron Corporation. All rights reserved.
2
LNG Train 2

Delivery of modules required for LNG Train 2 continues. All Train 1 modules and
13 of 17 Train 2 modules are on their foundations.
LNG Train 1
LNG Train 2
© 2015 Chevron Corporation. All rights reserved.
3
LNG and Condensate Tanks

Both LNG Tanks are now ready for LNG. Construction is complete on three of the
four condensate tanks.
LNG Tanks
Condensate Tanks
© 2015 Chevron Corporation. All rights reserved.
4
Domestic Gas Pipeline

The jetty is complete except for loading arm installation. The domestic gas
pipeline is now connected from the mainland through the jetty to the plant site
and pre-commissioning activities are complete.
Domestic Gas Pipeline Connection
© 2015 Chevron Corporation. All rights reserved.
5
Upstream Subsea Facilities Are Now Complete

All subsea pipelines, wellheads and associated facilities for Gorgon and Jansz-Io
fields are complete. All 18 subsea wells have been drilled and are complete.
Pre-commissioning activities are under way on the subsea facilities at both fields.
Tie-in Spool
© 2015 Chevron Corporation. All rights reserved.
6
Permanent Operations Facility

With permanent power to the permanent operations facility, the first members
of the operations team have commenced commissioning and monitoring
systems in the central control room.
© 2015 Chevron Corporation. All rights reserved.
7
Ground Flare

Construction and pre-commissioning activities are complete for one of the four
ground flare boxes.
© 2015 Chevron Corporation. All rights reserved.
8