ANNEX- I RWSSP – LIS Programme FIRST STEERING COMMITTEE MEETING Date : 23.12.2014 List of Participants S. No. Name Designation MoDWS 1. 2. 3. 4. 5. 6. Ms. Vijaylaxmi Joshi Mr. Saraswati Prasad Mr. Satyabrata Sahu Mr. Rajesh Kumar Mr. J.C. Singhal Mr. Arun Rustagi Secretary Joint Secretary (Sanitation) Joint Secretary (Water) Director, (Water & NPMU) Sr. Consultant, NPMU Sr. Consultant, NPMU World Bank 7. Ms. Smita Misra 8. Mr. Vijendra Vikrampandey Assam 9. 10. Task Team Leader Consultant (Technical) Mr. A.K. Das Mr. S.K. Baruah Secretary PHED Project Director Mr. Vinay Kumar Mr. D.P. Singh Project Director, SPMU Director, SPMU Bihar 11. 12. Jharkhand 13. Mr. Jabber Singh Secretary cum Project Director Uttar Pradesh 14. 15. 16. 17. Mr. P.K. Assudani Mr. C. K. Tyagi. Mr. R.M. Tripathi Dr. M.C. Pandey MD, UPJN Chief Engineer (Rural), UPJN Joint Director, UPJN Financial Advisor, SWSM/SPMU STEERING COMMITTEE MEETING RURAL WATER SUPPLY AND SANITATION PROJECT, ASSAM 23rd December 2014 Physical Progress Up to date Physical progress Vs Target Target Up to date progress i) Award of the project A. For Kamrup and Jorhat Project, Bidding and Evaluation process completed and NOC for award is accorded. B. Hailakandi Project under rebidding process. ii) iii) iv) v) vi) vii) viii) ix) SPMU formation EoI for DPMU Lead Training Agency Support Organization Independent Verification Agency IEC Capacity Building Baseline Survey A. SPMU formation completed with office establishment. A. EoI for DPMU floated, Short listing done. A. LTA selection done. A. Revised TOR prepared and submitted. A. IVA under process. A. IEC activity started. A. SPMU started CB activities for PHED officials. A. Baseline Survey going on through Tablet. Financial Progress: 9.9 Cr. Received from GOI Expenditure incurred 1.98 Cr. Action plan for last quarter year 2014-15. • Allotment of Kamrup and Jorhat project will be done and execution started . • Process of rebidding and work allotment of Hailakandi project to be done. • Finalization of LTA . • Finalization of SO. • Finalization of IVA. • Physical formation of MVWSC. • Expedition of Base line survey through Tablet. • GP level sensitization already done in 47 GP’s out of63 numbers of GP’s and remaining 16 nos of GP will be covered during the last quarter year. • DPMU will be make functional. • Sensitization program started in school and AWC under Swachh Bharat Abhiyan. • Intensive IEC & Capacity Building will continued. Annual Action Plan -2015-16 1.Physical progress and execution of Jorhat and Kamrup project. 2. All activities of Swachh Bharat Abhiyan will be undertaken. 3. Preparation of DPR for SLWM. 4. Initial work for Batch-2 project wiil be initiated (Baseline survey, Environmental Assessment Studies, Social Assessment Studies). 5. IEC & CB will be implemented in a mission mode QUARTER WISE FUND REQUIREMENT(2015-16) • 1st quarter • 2nd quarter • 3rd quarter • 4th quarter - 30 crores 30 crores 50 crores 100 crores Release of GoI, State & Community Share • Rs. 9.99 Cr. Received from GoI CONSTITUTION OF COMMITTEES & OTHER STATUS •GPWSC- Functional & new account of GPWSC for RWSSP is already initiated. • MVWSC already formed. • Independent Verification Agency not yet finalized. • LTA selected & contract negotiation done. MoU to be signed. Sanitation & SLWM • Preparation of DPR for SLWM already initiated in association with Swachh Bharat Mission, PHED, Assam. • School sanitation & hygiene education program is going on under RWSSP-LIS. • Interpersonal Communication started in project areas mainly for toilet construction where baseline survey started. • Convergence in inter-departmental level already done for SBM • IEC & Capacity Building strategy of RWSSP-LIS includes sanitation related initiatives. THANKs SPMU,ASSAM Neer Nirmal Pariyojana, Bihar (Rural Water Supply & Sanitation Project) 1 Physical Progress Component – A (Capacity Building & Sector Development) Launched on 21st June 2014 by the Hon’ble Minister, PHED. Three State-level Workshops organized for SPMU/DPMU officials /specialists, District Coordinators/Block Coordinators of NBA and PRI Representatives. Three District-level Launch-cum-Orientation Workshops organized for District-level officers, elected representatives of concerned GPs and other stakeholders. 43 GP-level meetings conducted. 560 GP Representatives & other stakeholders attended the meetings. 76 hoardings, 565 wall writings, 139 Nukad Nataks, numerous roadshows & household visits conducted Baseline survey under progress in project area of MVS. Component – B (Infrastructure Development) All four MVS of Batch-1 (Cheriya, Ghoghaghat, Rajauli & Silao) awarded (Rs 272 cr), agreement executed, mobilization advance (Rs 16.39 crores) released and work is under progress. 136 DPRs of SGS/SHS against 152 schemes of Batch – 1 prepared and under process of sanction and remaining schemes under preparation. Tenders for 8 SGS/SHS under process; 3 to be finalized shortly. Consulting firms shortlisted for DPMC and RFP to be issued shortly after NoC from the World Bank to the shortlisted firms. Component – C Project Management Support. SPMU & DPMU established and functional. All 7 SPMU Specialists placed and selection of DPMU specialists under process (posts advertised) GO for delegation of power to Project Director issued. Financial Progress Total Project cost: - Rs. 1606 Cr. (Component A -117 Cr., Component B – 1413 Cr., Component C - 76 Cr.) Fund Received (Rs. In crore) EAP (World Bank) Share GoI share State share Community Share Total 9.99 5.49 4.30 0.00 19.78 Fund transferred to SPMU account – 19.78 Fund allocation during 2014-15 – 121 Fund released during 2014-15 - Nil Total fund available 19.78 Expenditure till date - 17.47 Details of IUFR submitted Period Amount (component wise) Total A B C 31st March’ 13 to 6th Feb’14 3,327,168 0 6,58,149 39,85,317 7th Feb, 14 to 31st Mar’14 0 0 2,98,032 2,98,032 1st Apr’14 to 30th June’14 0 0 3,93,220 3,93,220 1st July’14 to 30th Sep’14 36,99,180 8,56,94,000 9,85,159 9,03,78,339 Total 70,26,348 8,56,94,000 23,04,560 9,50,24,908 Proposal for release of 1st installment of EAP (World Bank) share during current year has been submitted to GoI with a copy to 4 World Bank. Action Plan (Last Quarter, 2014-15) Capacity Building and Sector Development Agreement with Lead Training Agency and ToT of its resource persons. Training and workshop on project components for officials/specialists of SPMU/DPMU/DPMC/SO/GP functionaries and other stakeholders. Baseline survey for the first batch – MVS/SGS. Exposure visit to other world Bank supported project States, e.g, Kerala, Punjab, Uttarakhand etc. Conducting various IEC/BCC activities like hoardings, wall writings, road shows, nukkad natakas, IPC & media campaign. Infrastructure Development Monthly/fortnightly monitoring/ review of the Progress of MVS at District & State level. Bids to be finalized and work awarded for SHS/SGS schemes of Batch-1. Hiring and placing of District Project Management Consultants (DPMC) with SOs. Hiring and placing of Independent Verification Agency (IVA). Project Management Support Issuing GO with guidelines for co-opting two GP standing committees for water supply & Sanitation schemes . Hiring of specialists for DPMUs. Establishing separate offices with all infrastructure facilities for SPMU & DPMUs. Hosting & managing websites for the project to facilitate web-based (IMIS) & grievance redressal system. Providing CUG & Laptops facilities to officials & Specialists. Hiring services of Auditing firm. Action Plan for 2015-16 Component – A •Nine State-Level Workshops /Refresher Training Programmes. •Two international exposure visits (comprising 8 participants each batch). •Four state-level exposure visits (comprising 25 people each batch). •Seventy-four district-level workshops /training of different stakeholders. •1062 Panchayat-level training/orientation programmes. •Organizing phase wise IEC campaign. •Fully operational IMIS system. •Impact Assessment Studies. •Study on sanitation practices/uses of toilets. Component – B Implementation phase for Batch – 1 SHS/SGS schemes under progress. Implementation phase for Batch – 1 MVS schemes under progress. DPRs for SLWM activities for pilot villages will be prepared and work will be started. DPMCs fully operationalized. 6 6 Action Plan for 2015-16 Component - C Fully functional DPMUs. Fully functional Project specific websites for web based project monitoring system. All GP & MVS level committees under Batch -1 to be fully functional. Hiring services of consultants/specialists under sanitation cell at SPMU/DPMU level. Quarterly fund requirement for 2015-16 (Rs in crores) Quarter Component - A Component - B Component - C Total 1 4.75 67.59 6.87 79.21 2 3.17 37.32 4.86 45.35 3 2.91 32.02 4.78 39.71 4 3.82 32.02 4.78 40.62 Total 14.65 168.95 21.29 204.897 Constitution of Different Committees Government Orders Draft GO authorizing GP-level standing committees, i.e Public Works Committee and Public Health, Family Welfare, Rural Sanitation Committee for carrying out Water Supply & Sanitation schemes respectively sent to PRD for its consent. GO related to Multi Village Committee will be issued after issuance of aforesaid GO. Independent Verification Agency (IVA) A consulting firm has been shortlisted from 7 bids received based on best qualifications and references following CQS procedure. The RFP will be issued shortly to the selected firm after incorporating the observations of the World Bank. Lead Training Agency (LTA) Lead Training Agency,namely CIMP, has been identified following SSS procedure. Technical & Financial proposal received and under scrutiny and negotiation for entering into MoU. 8 Sanitation & SLW Management Sanitation cell in SPMU and DPMU to be established. 10 villages (large, medium & small), one from each district have been selected for piloting SLWM. Bids for hiring consultants for preparation of SLWM DPRs received and are under evaluation. 9 Issues Release of 1st instalment of EAP (World Bank) share during current year. DPRs cost for the water supply schemes based for on current SoR and market rate exceeding the cost envisaged in PIP on the basis of rough per capita cost. Poor response of bidders to participate in the biddings of schemes under the World Bank project because of stringent qualifying criteria. 10 Thanks 11 RURAL WATER SUPPLY & SANITATION PROJECT RWSSP-LIS SPMU, JSWSMS JHARKHAND Physical & Financial Progress Component A –Capacity Development & Sector Development • • The CB and IEC plan for the state & district developed (2014-15-16). RFP has been issued to XISS, Ranchi for hiring it as Key Resource Agency Component B – Infrastructure Development • For Batch I, bids against 48 schemes were received, only 32 (no.) bidders qualified out of which which 22 bids are in position to be awarded work order. Work order to be given before 31st December 2014 • 9 MVS bidded out. Bids against 7 schemes were received & 2 schemes will be bid out again. • For remaining 5 bids, work order will be issued by Jan 2015. • 2 MVS are in the process of rebidding. Component C – Project management Support • SPMU,DPMU offices established with required manpower • DPMC hired for 4 districts. SPMU will be acting DPMC for remaining 2 districts • IUFR for 2nd quarter submitted to GOI/WB via letter no. JSWSM/WB/UC-06/2014-401 dated 3.12.14 • Procurement Plan for 18 months developed • Implementation of HR Manual. • TDP specialist, Dy Director Finance& Superintending Engineer at SPMU placed Release of GOI, State & community share for Project (Fig in Cr.) Sl Entity Sanctioned amount Received from Expenditure PMU (up to sept 14) (NRDWP) Balance 1 World Bank 09.99 09.99 02.72 07.27 2 Govt. of India 05.79 00.00 00.00 00.00 3 State Govt. 04.00 00.00 00.00 00.00 4 Community Contribution 00.20 00.00 00.00 00.00 Total 19.98 09.99 02.72 07.27 Annual Action Plan for the year 2015-16 including last quarter 2014-15 • Batch I DPRs preparation & Awarding of Contract (Total 326 schemes) DPRs (no.s) Bidded out Bidding/Rebidding 60 SVS bidded + 178 DPRs under process 22 SVS Work order to be issued & 10 SVS will be issued after SLSSC approval (Total 32 SVS ready for work order) 28 (60-32) + 178 =206 To be bidded out & work order to be awarded by this financial year. 98 DPRs to be prepared by Feb, 15 By Mar, 15 Batch I = 60+178+98 =326 SVS All Schemes Bidded out by Mar 15 2015-16 Implementation of Batch I schemes and Batch II preparation • Detail Action Plan for 2014-15-16 developed (physical & financial attached) Constitution of different committees, IVA, Lead Training Agency • Village Water & Sanitation Committees formed in Batch I villages ( approx. 350 numbers). • Project specific Tender Committee, Review committee, Purchase committee constituted. • IVA – RFP issued & proposal submission deadline is 22.12.2014 • LTA- Technical & financial proposal submitted by the agency. Committee formed to review the proposal. Sanitation and SLWM • 6 model DPR for solid and Liquid waste management being prepared • EOI published, shortlisting done and RFP issued to the shortlisted firm • Draft sanitation plan for one habitation prepared. Sanitation plan for 3 villages(5 habitation) being prepared Prioritization of project GP for NBA funding: • Batch 1 GP list shared with district and state NBA cell. • Sanitation component Prioritized in identified GPs and included in NBA- AIP-2014-15 Issues & Constraints • Addressing the slip back toilets constructed under the earlier TSC fund provisions( Number 4-5 lakhs. in project district) • Provision of exemption of excise duty on prefabricated toilets materials. Excise exemption is already their in water supply • The present fund flow in sanitation from district to VWSC results in delays, which can be addressed if the same fund flow arrangement for WSS is adopted in case of sanitation. THANKS RURAL WATER SUPPLY AND SANITATION PROJECT SPMU, UP A Presentation for the Steering Committee Meeting Dated 23-12-2014 S No 1. Action PHYSICAL PROGRESS Target Progress as on 22nd December 2014 Capacity Building: (i) Hiring of Training Support & 15th December 2014 Mentoring Agency Agreement signed on 12/12/2014. ToT to commence in 3rd week of January 2015. (ii) Hiring of Support Organizations Hiring of Lead Training Agency Baseline Survey Latest by January 31, 2015 By December 31, 2014 Technical Bids under evaluation. Technical Evaluation reports shall be sent to WB by 31/12/2014 for NOC. Revised draft contract sent to WB for NOC. By March 31, 2015 Hiring of Independent Construction Quality and Surveillance (ICQS) Consultant Developing web-site with district-wise details on targets and achievements By January 31, 2015 Tablet Computers under procurement. IFB issued. Corrigendum issued. Last date is 02/01/2015. Under process. Shortlisting Completed. RFP issued. By December 15, 2014 Web pages of all 10 districts developed. Implementing web-based M&E and Reporting System Immediate effect for baseline survey Baseline Survey conducted in 2 pilot GPs for testing of the application. M&E software developed by M/s Mobile Pedia hired by WB (iii) (iv) (v) (vi) (vii) PHYSICAL PROGRESS 2. Infrastructure: (i) Awarding all Batch I MVSs Target Achievement upto 22/12/2014 Latest by Decision on award of 1 MVS of Allahabad March 31, taken. Decision on 1 MVS of Gonda and 2 2015 (state MVS of Behraich to be taken by details in 24/12/2014. Retendering for rest MVS to Procurement be done by 26/12/2014 Section) (ii) Awarding all Batch I 3 schemes of Allahabad awarded under SVSs local shopping. Decision on Bids for 16 SVS to be taken by 26/12/ 2014. Bids for all remaining 200 SVS of 9 Districts to be invited by 26/12/2014. (iii) Implementing program DPR for one GP Palpur, Distt. Allahabad for pilot SLWM prepared by UPJN and will be sent to WB schemes for approval by 24/12/2014. Based on this DPR all other 8 pilot DPRs will be FINANCIAL PROGRESS Financial Position in Rs Lakhs Upto From April 2014 to 17th Since Inception 31 March 2014 December 2014 Funds Received: GOUP GOI World Bank Total Expenses : 1 Component (A) Capacity & Sector Development 2 Component (B) 3 Component (C) Project Management Support Total 0.00 0.00 366.00 613.00 366.00 613.00 0.00 0.00 999.00 1978.00 999.00 1978.00 25.48 22.18 47.66 0.00 239.24 0.00 149.01 0.00 388.25 264.72 171.19 435.91 ACTION PLAN FOR LAST QUARTER YEAR 2014-15 Financial Plan Component A Training by TSMA Training by SIRD Exposure Visits IEC Activities- Media Agency Media Agency Radio Jingles, Documentary Film etc Sector Development Studies M&E Activities Procurement of Tablets Concurrent Monitoring & Process Documentation Support Organizations Component B Water Supply Sanitation/ SLWM Water Quality Management (Labs) Engg. Support(WS & Sanitation) Project Cell- UPJN Project Cell- PRD ICQSC Component C SPMU & DPMU Establishment Total FY 2014-15 Q4 21.68 10.00 10.00 15.00 25.00 10.00 26.00 30.00 200.00 6080.00 699.34 90.00 858.00 20.00 6.00 9.00 95.00 8205.02 QUARTER WISE ACTION PLAN FOR YEAR 2015-16 Financial Plan Q1 Component A Training by SIRD Exposure Visits IEC Activities- Media Agency Media Agency Radio Jingles, Documentary Film etc Sector Development Studies M&E Activities Procurement of Tablets Concurrent Monitoring & Process Documentation Support Organizations Component B Water Supply Sanitation/ SLWM Water Quality Management (Labs) Engg. Support(WS & Sanitation) Project Cell- UPJN Project Cell- PRD ICQSC Component C SPMU & DPMU Establishment Total FY 2015-16 Q2 Total Q3 Q4 41.00 0.00 41.00 10.00 41.00 0.00 41.00 10.00 15.00 25.00 0.00 25.00 0.00 25.00 25.00 10.00 10.00 10.00 10.00 15.00 30.00 15.00 30.00 15.00 30.00 15.00 0.00 100.00 200.00 200.00 200.00 6080.00 6080.00 6080.00 6080.00 650.01 85.00 689.00 15.00 20.00 13.50 2486.67 150.00 918.00 12.00 5.00 13.50 2927.51 150.00 973.00 5.00 5.00 13.50 2927.51 0.00 973.00 5.00 5.00 13.50 90.00 7878.51 50.00 10046.17 50.00 10525.01 50.00 10355.01 164.00 20.00 0.00 15.00 100.00 40.00 0.00 60.00 90.00 700.00 0.00 24320.00 6064.19 385.00 2580.00 37.00 35.00 54.00 0.00 240.00 34904.19 CONSTITUTION OF DIFFERENT COMMITTEES • State Level Scheme Sanctioning Committee (SLSSC) formed under NRDWP gives the Administrative Sanctions of all Schemes and Annual Action Plans • Gram Panchayat Water & Sanitation Committees (GPWSC) have been formed in all the Batch 1 GPs. • Multi Village Water and Sanitation Committees (MVWSC) are under formation. • Independent Construction Quality and Surveillance Consultant is being appointed. ToR approved by WB. EOI invited and 6 agencies shortlisted. RFP has been issued • Centre for Good Governance, Uttarakhand Academy of Administration, Nainital appointed as Training Support and Mentoring Agency (TSMA). Agreement signed on 12/12/2014 • Centre for Development Action, State Institute of Rural Development (SIRD), Lucknow has been identified as LTA. Negotiations are complete. Agreement will be signed in December 2014 • Neer Nirmal Pariyojna Cell (RWSSP) has been formed at State Level at UPJN Hq for providing support to project district & GPs for implementation of water and sanitation activities SANITATION & SLWM • All RWSSP-GPs have been included in Swachh Bharat Mission – Rural (SBM) Annual Implementation Plan 2014-15. • State Sanitation Coordinator, SBM and all 10 RWSSP-District officers of Panchayti Raj Department (DPRO & DPC- SBM) have been oriented with Sanitation project cycle and Sanitation components in RWSSP and community led approach in State level Workshops. • Exposure visit for State Sanitation Coordinator, SBM and DPROs have been conducted for hands-on experience on Sanitation components and Bio-Gas plant in Calicut, Kerala. • Uttar Pradesh Jal Nigam has been assigned role of technical agency for preparation of SLWM DPRs and will provide technical support to Project GPs during implementation of SLWM. 9 project GPs has been selected for piloting SLWM plan. • Neer Nirmal Pariyojna Cell (RWSSP) has been formed for providing support to project district & GPs for implementation of sanitation activities. • Total Progress of RWSSP districts during 2014-15 is as follows: Target- 338194 IHHL Progress- 65469 (19.36%) (source PRD) • Brainstorming workshop has been organized on 12/11/2014 with World Bank, State and 10 project district officers (DDO/DPRO and DPC) for assessment of resources and problems faced in implementation of SBM for creating ODF district by adopting district wide approach for the achievement of the target of Clean India by 2019. • Pilot GPs have been oriented on sanitation component and IEC activities have been conducted in the GPs. ISSUES AND CONSTRAINTS • Contractors in UP lack experience for working on turn key basis and are not familiar with the e-tendering process. Due to this in spite of 3 rounds of tendering, the response from bidders has been very poor, so far. • Workshops are being conducted in each project district for building capacity of prospective bidders on e-tendering and to facilitate their registration on e-tendering portal. • Funds have still not been made available to the Batch-1 GPs for Toilet Construction and SLWM works due to which work has not commenced in the GPs PHYSICAL PROGRESS 3. Project Management: (i) (ii) 4 (i) SPMU established. However, need for dedicated PDs with adequate devolution of authority DPMUs partially established Target Achievement upto 22/12/2014 Dedicated PD urgently needed SPMU fully established. CEO nominated to coordinate day to day activities of SPMU. DPMUs to be fully staffed DPMUs fully functional with DDO and functional, latest by as District Project Manager, EE, Feb15, 2015 UPJN as Technical-cumProcurement Consultant and DWSC Consultants as Subject Specialist, Accountants Officer of DRDA as Accounts Manager. GO No 1349 dated 20/10/2014 issued to make this entity functional Financial Management Submission of audit report By December 31, 2014 for FY 13-14 Audit in process
© Copyright 2024