2015 district 4 construction program

DISTRICT 4
2015 C ONSTRUCTION P ROGRAM
SERVING ASHTABULA, MAHONING, PORTAGE, STARK, SUMMIT AND TRUMBULL COUNTIES.
JOHN R. KASICH, OHIO GOVERNOR | JERRY WRAY, ODOT DIRECTOR | ANTHONY M. URANKAR, DISTRICT DEPUTY DIRECTOR
2015 DISTRICT 4 CONSTRUCTION PROGRAM
2015 Construction Program
Total Costs: $563.1 million - Construction Costs: $503.9 million
Thank you for your interest in Ohio Department of Transportation - District 4’s 2015 Construction Program. This publication is intended to provide
a general overview of projects that currently are under construction and those scheduled to be awarded or begin construction in 2015.
The 2015 Construction Program is divided into six sections, one representing each county in District 4. Award dates, expected
completion dates, project descriptions, project locations, cost and maintenance of traffic are listed. Total costs include preliminary
engineering, right-of-way and construction. County maps have also been included for your reference.
Please keep this book on hand throughout the upcoming construction season. Information regarding construction projects is continually changing;
therefore, if you have any questions or require additional information, please do not hesitate to contact us or visit the District 4 website at
http://www.dot.state.oh.us/districts/d04/Pages/default.aspx for updates. District 4 utilizes Facebook and Twitter! Please like us at our Ohio Department of
Transportation Akron / Canton District 4 page and follow us on Twitter at ODOT_Akron.
STATEWIDE TRANSPORTATION INITIATIVES CONTINUE AT DISTRICT 4
Two innovative and exciting statewide programs continue and begin in District 4 with projects highlighted in the following pages of the 2015
Construction Book. The Ohio Bridge Partnership Program (OBPP) is a new construction initiative designed to reduce the excess of deficient county
bridges. ODOT works cooperatively with Ohio’s County Engineers and municipalities to replace bridges in need of repair and/or replacement.
The statewide OBPP provides $120 million from State Fiscal Year 2015 – 2017 for the replacement of bridges. In District 4, 17 bridges as part of
the OBPP will be replaced in Portage, Stark and Trumbull Counties. The projects are highlighted on pages 17, 22 and 35.
On page 13, the second project accelerated by Governor John Kasich’s Jobs and Transportation Plan, the widening of Interstate 80 in Mahoning
and Trumbull Counties is highlighted. This project along with the widening of Interstate 271 in Summit County (page 26), which broke ground last
construction season, were made possible by an innovative plan to issue bonds backed by turnpike toll revenue dedicated exclusively to Northern Ohio. The
Jobs and Transportation Plan helps fill ODOT’s budget deficit without raising taxes that would kill jobs. The entire plan injects nearly $3 billion in state,
local and federal, and turnpike money into 41 transportation projects across the state. These needed funds erase delays and accelerate most construction
projects by more than 10 years.
District 4 Public Information Office 330-786-2208
OVERVIEW
Printed: January 2015
2
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Construction Outreach at ODOT District 4
During the 2014 Construction Season the District 4 Public Information Office continued its expanded
outreach to inform motorists, residents and businesses of any construction projects causing significant
maintenance of traffic issues.
One of the key components to this outreach is the use of Closure Notification Brochures on high
impact projects around the district. These brochures identify construction projects that have large
maintenance of traffic impacts in areas that may affect businesses. The Closure Notification Brochures
explain the construction project, the maintenance of traffic, the amount of time motorists and businesses
will be impacted and include detailed detour maps for the area.
If a project is deemed to have a Closure Notification Brochure created, these documents are handed out
to local officials, residents and businesses. A representative from the District 4 Public Information
Office will typically be joined by a construction project engineer and will distribute the brochures door
to door within or near the construction project.
Projects marked with a red asterisk (*) in this book are projects that the Public Information Office will
include Closure Notification Brochures during the 2015 construction season. In the upcoming year, the
Public Information Office has identified 16 projects where brochures will be distributed to businesses
in the surrounding area.
ROAD WILL BE
CLOSED MAY 14
FOR 90 DAYS
INFO: 330-786-2208
OVERVIEW
Also in 2014, District 4 continued to place signs along bridge and ramp closures that provided a
contact information number if motorists had questions regarding a construction project or a closure
associated with the project. These orange signs let motorists know that a roadway will be closed for a
certain number of days and provided a phone number to the Public Information Office if they had
any questions. Motorists can look for these signs again in 2015.
3
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Ashtabula County
Upcoming: $8.5 million
Construction Costs:
Active: $82.2 million
Total: $90.7 million
4
ASHTABULA COUNTY
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Ashtabula County Active Projects
*
US Route 20
Ashtabula Township
PID: 77563
CONSTRUCTION COST: $2.9 million
START DATE: March 2015
PROJECT: 14-269
TOTAL COST: $6.2 million
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Resurfacing on US 20 from Vineland Avenue to
Cook Road. The project includes the installation of sidewalks and drainage
improvements on US 20 from SR 11 to Cook Rd. and the widening of US 20 to
add a two way left turn lane from Ridgewood Rd. to Cook Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on US 20 during construction. Access to Walmart will
be maintained through Metcalf Dr. Access to all residences and businesses will be
maintained at all times throughout construction.
*
US Route 20
Interstate 90
Austinburg, Saybrook & Plymouth Townships
PID: 76747
CONSTRUCTION COST: $68 million
START DATE: February 2013
PROJECT: 12-0625
TOTAL COST: $70.6 million
COMPLETION DATE: Nov. 2016
PROJECT DESCRIPTION: Pavement replacement on I-90 from just east of Clay
St. to the Penn Central Railroad. This project also includes modifications to the SR
11 and I-90 interchange, as well as bridge rehabilitations to two bridges on I-90
and five overhead bridges. Work completed in 2014 included the replacement of I90 eastbound from SR 45 to Chapel Rd., the replacement of the Chapel Rd. bridge
over I-90, the Jefferson Rd. bridge over I-90 and the replacement of the SR 11
northbound bridge over I-90. Work to be completed in 2015 includes the
replacement of I-90 westbound between Chapel Rd. and SR 11, the replacement of
the I-90 westbound ramps at SR 11, the completion of the new SR 11 northbound
ramp to I-90 eastbound and the elimination of the SR 11 bridges over Carson Rd.
MAINTENANCE OF TRAFFIC: Two lanes of traffic will be maintained on I-90
during peak travel periods. Ramp closures at I-90 and SR 11 will occur for 180
days. All detours will be posted. Access to all businesses and residences will be
maintained at all times throughout construction.
Village of North Kingsville & City of Conneaut
PID: 83599
CONSTRUCTION COST: $11.3 million
START DATE: March 2015
PROJECT: 14-537
TOTAL COST: $13.4 million
COMPLETION DATE: June 2016
PROJECT DESCRIPTION: Replace the US 20 bridge at the border of the Village
of North Kingsville and City of Conneaut between Overpass Drive and Industry
Road.
MAINTENANCE OF TRAFFIC: US 20 will be closed for 270 days. Access to
Industry Road will be maintained at all times. A detour will be posted. Access to
all residences and businesses will be maintained at all times throughout
construction.
ASHTABULA COUNTY
5
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Ashtabula County Upcoming Projects
Ashtabula County Culvert Replacements
Various Locations
PID: 95133
ESTIMATED CONSTRUCTION COST: $400,000
ESTIMATED TOTAL COST: $500,000
AWARD DATE: May 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Culvert replacements on various routes throughout
Ashtabula County including: two culverts on SR 45, one just north of Winters Rd.,
and one just south of SR 307, and one culvert on SR 534 between Stoneville Rd.
and SR 86.
State Route 534
Harpersfield & Trumbull Townships
PID: 86943
ESTIMATED CONSTRUCTION COST: $1.7 million
ESTIMATED TOTAL COST: $1.7 million
AWARD DATE: June 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Resurfacing of SR 534 from Barrett Rd. to the
southern Geneva Corporation limit. The project also includes miscellaneous bridge
repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers throughout construction.
MAINTENANCE OF TRAFFIC: Traffic will be detoured for each culvert
replacement. Detours will be posted. At all other times, a minimum of one lane of
traffic will be maintained. Access to all residences and businesses will be
maintained at all times throughout construction.
State Route 11
Dorset, Lenox, Cherry Valley and New Lyme Townships
PID: 83037
ESTIMATED CONSTRUCTION COST: $6.4 million
ESTIMATED TOTAL COST: $6.4 million
AWARD DATE: July 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Resurfacing of SR 11 from just north of US 6 to just
south of SR 307. The project also includes bridge repairs to five bridges, including
one over Mill Creek, Sentinel Rd. over SR 11, Allen Comp Rd. over SR 11,
Footville Richmond Rd. over SR 11 and Mill Rd. over SR 11.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 11 at all times.
ASHTABULA COUNTY
6
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Mahoning County
Construction Costs:
Active: $34.1 million
Upcoming: $113 million
Total: $147.1 million
MAHONING COUNTY
7
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Mahoning County Active Projects
Interstate 76
Milton Township
US Route 62
City of Youngstown
PID: 24073
CONSTRUCTION COST: $16.9 million
START DATE: April 2014
PROJECT: 14-0037
TOTAL COST: $19.2 million
COMPLETION DATE: June 2016
PROJECT DESCRIPTION: Rehabilitation of the bridge on US 62 over SR 289,
the Mahoning River and railroad. The rehabilitation includes replacing the deck,
expansion joints and parapets as well as steel and concrete strengthening repairs.
The ramps to Himrod Avenue will also be reconstructed as part of this project.
Work completed in 2014 included the beginning of the replacement of the US 62
westbound structure. Work to be performed in 2015 includes the completion of the
westbound structure replacement and the beginning of the eastbound structure
replacement.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained in each
direction on US 62. The entrance and exit ramps at Himrod Ave. and South Ave.
will be closed for 12 months. All detours will be posted. Access to all residences
and businesses will be maintained at all times throughout construction.
PID: 93887
CONSTRUCTION COST: $2.9 million
START DATE: November 2014
PROJECT: 14 - 0352
TOTAL COST: $3.3 million
COMPLETION DATE: June 2015
PROJECT DESCRIPTION: Construction of noise walls along I-76 at the Lake
Milton area. Work completed in 2014 included embankment work, drainage
repairs and foundation construction for noise walls. Work to be completed in 2015
includes construction of noise walls and additional drainage repairs.
MAINTENANCE OF TRAFFIC: Two lanes of traffic will be maintained on I-76
during peak travel hours. A minimum of one lane in each direction will be
maintained during non-peak travel hours throughout construction.
US Route 224
*
City of Canfield; Canfield Township
PID: 85245
CONSTRUCTION COST: $5.4 million
START DATE: March 2015
PROJECT: 14-0494
TOTAL COST: $6.5 million
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Replacement of the US 224 bridge over SR 11.
Project also includes the widening of SR 11 and Raccoon Rd. to install additional
lanes and turn lanes and the installation of an additional left turn lane on the SR 11
southbound ramp to US 224.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on US 224. Southbound traffic on Raccoon Rd. will
be detoured for 60 days.
MAHONING COUNTY
8
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Mahoning County Active Projects Continued
State Route 164 (Western Reserve Rd.)
*
Boardman & Beaver Townships
PID: 84754
CONSTRUCTION COST: $8.9 million
START DATE: April 2014
PROJECT: 13-3017
TOTAL COST: $9.7 million
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Replacement and widening of the SR 164 (Western
Reserve Rd.) bridge over I-680. This project also includes intersection
improvements with an additional westbound right turn lane on Western Reserve
Rd. at I-680 northbound entrance ramp. Project also includes the resurfacing of I680 from US 224 to the Pennsylvania Turnpike with minor bridge repairs. Work
that was completed in 2014 included the resurfacing of I-680 from US 224 to the
Pennsylvania Turnpike. Work to be completed in 2015 includes the replacement
and widening of the Western Reserve Rd. bridge over I-680 and all intersection
improvements.
MAINTENANCE OF TRAFFIC: I-680 under SR 164/Western Reserve Rd. will
have various lane restrictions. Western Reserve Rd. will be closed for 75 days. A
detour will be posted. Access to all residences and businesses will be maintained
throughout construction.
MAHONING COUNTY
9
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Mahoning County Upcoming Projects
Mahoning County Culvert Replacements
Various Locations
PID: 94529
ESTIMATED CONSTRUCTION COST: $800,000
ESTIMATED TOTAL COST: $1.2 million
AWARD DATE: June 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Culvert replacements on various routes throughout
Mahoning County including: one on SR 46 between Kirk Rd. and New Rd., one on
US 62 at Mellinger Rd., two on SR 14, one between Cunningham Rd. and Egypt
Rd. and one at Lisbon Rd., three on SR 165, one between SR 164 and Blosser St.,
one between SR 626 and SR 7 and one between the Columbiana County line and
Beard Rd. and one culvert on SR 616 between Oak St. and McGuffey Rd.
State Route 7/McClurg Rd.
Boardman Township
PID: 98694
ESTIMATED CONSTRUCTION COST: $700,000
ESTIMATED TOTAL COST: $800,000
AWARD DATE: April 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Widening of McClurg Rd. from SR 7 to just west of
Southern Blvd. The project also includes signal work at McClurg Rd. and SR 7 and
drainage repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on McClurg Rd. A minimum of one lane of traffic in each
direction will be maintained on SR 7.
South Ave.
MAINTENANCE OF TRAFFIC: Traffic will be detoured for each culvert
replacement. Detours will be posted. At all other times, a minimum of one lane of
traffic will be maintained. Access to all residences and businesses will be
maintained at all times throughout construction.
City of Youngstown
PID: 87408
ESTIMATED CONSTRUCTION COST: $1.3 million
ESTIMATED TOTAL COST: $1.7 million
AWARD DATE: May 2015
COMPLETION DATE: Dec. 2015
PROJECT DESCRIPTION: Upgrading traffic signals on Midlothian Blvd.
between South Ave. and Southern Blvd. and on South Ave. between Midlothian
Blvd. and just south of I-680. Project also includes ADA ramps and crosswalks.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained at all times by flaggers.
MAHONING COUNTY
10
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Mahoning County Upcoming Projects Continued
State Route 164
Beaver Township
US Route 62
Green Township
PID: 97931
ESTIMATED CONSTRUCTION COST: $300,000
ESTIMATED TOTAL COST: $300,000
AWARD DATE: April 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Replace the bridge on US Route 62 over the Meander
Creek between Calla Rd. and Knauf Rd.
MAINTENANCE OF TRAFFIC: US Route 62 will be closed for a period of 14
days. A detour will be posted. Access to all residences and businesses will be
maintained at all times throughout construction.
Interstate 80
*
Austintown, Weathersfield & Liberty Townships; City of Girard
PID: 77260
ESTIMATED CONSTRUCTION COST: $97.6 million
ESTIMATED TOTAL COST: $108.4 million
AWARD DATE: April 2015
COMPLETION DATE: July 2018
PROJECT DESCRIPTION: Pavement replacement and widening on I-80 from
four to six lanes between SR 46 and SR 193/Belmont Ave. in Trumbull County.
The project also includes the widening and replacement of six bridges on I-80.
PID: 93487
ESTIMATED CONSTRUCTION COST: $5 million
ESTIMATED TOTAL COST: $5.3 million
AWARD DATE: June 2015
COMPLETION DATE: October 2016
PROJECT DESCRIPTION: Replacement and widening of the SR 164 bridge over
I-680.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 164 throughout construction.
State Route 289/US Route 422
City of Youngstown
PID: 86949
ESTIMATED CONSTRUCTION COST: $2.3 million
ESTIMATED TOTAL COST: $2.3 million
AWARD DATE: April 2015
COMPLETION DATE: August 2015
PROJECT DESCRIPTION: Resurfacing of SR 289 between Himrod Ave. and the
City of Campbell Corporation limit and the resurfacing of US 422 from the
Trumbull County line to SR 193. The project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction of I-80 during non-peak travel times. Various ramp
closures will occur throughout construction. All detours will be posted. Access to
all residences and businesses will be maintained at all times throughout
construction.
MAHONING COUNTY
11
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Mahoning County Upcoming Projects Continued
Interstate 680
City of Youngstown
US Route 422
Coitsville Township
PID: 84597
ESTIMATED CONSTRUCTION COST: $1.3 million
ESTIMATED TOTAL COST: $1.3 million
AWARD DATE: January 2015
COMPLETION DATE: August 2015
PROJECT DESCRIPTION: Resurfacing of US 422 from SR 616 to the
Pennsylvania State line. The project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flagger.
MAHONING COUNTY
PID: 82941
ESTIMATED CONSTRUCTION COST: $3.7 million
ESTIMATED TOTAL COST: $4.2 million
AWARD DATE: October 2015
COMPLETION DATE: October 2016
PROJECT DESCRIPTION: Rehabilitation of the Vestal Rd. bridge over I-680.
The project also includes improvements to the Vestal Rd. and Hazelwood Ave.
intersection.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic in each
direction will be maintained on I-680 under Vestal Rd. Vestal Rd. over I-680 will
be closed for 180 days. Hazelwood Ave. will be closed for 45 days. All detours
will be posted. Access to all residences and businesses will be maintained at all
times throughout construction.
12
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Portage County
Construction Costs
Active: $5.5 million Upcoming: $12.4 million
Total: $17.9 million
13
PORTAGE COUNTY
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Portage County Active Projects
State Route 44
Shalersville Township & Village of Mantua
State Route 14
Ravenna & Edinburg Townships
PID: 82916
CONSTRUCTION COST: $3.9 million
START DATE: October 2014
PROJECT: 14-8025
TOTAL COST: $3.9 million
COMPLETION DATE: July 2015
PROJECT DESCRIPTION: Resurfacing of SR 14 from SR 88 to SR 183. Project
also includes minor bridge repairs, three culvert replacements and the realignment
of Hayes Rd. and SR 14. Work that was completed in 2014 included the
replacement of a culvert on SR 14 just north of I-76. Work to be completed in 2015
includes two culvert replacements, the realignment of Hayes Rd. and SR 14 and
the resurfacing of SR 14 between SR 88 to SR 183.
PID: 82913
CONSTRUCTION COST: $1.6 million
START DATE: July 2014
PROJECT: 14-0256
TOTAL COST: $1.8 million
COMPLETION DATE: June 2015
PROJECT DESCRIPTION: Resurfacing of SR 44 from SR 303 to Mill St. in the
Village of Mantua. Project also includes minor bridge repairs, a bridge replacement
between Orchard St. and Canada Rd. and the installation of sidewalks in the
Village of Mantua. Work completed in 2014 included the bridge replacement on
SR 44 between Orchard St. and Canada Rd. Work to be completed in 2015
includes the resurfacing of SR 44 between SR 303 and Mill St.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained by
flaggers on SR 44 at all times.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained by
flaggers throughout construction. Except for a period of 21 days when SR 14 will
be closed for culvert replacements. Hayes Rd. will be closed for 14 days. All
detours will be posted. Access to all residences and businesses will be maintained
at all times throughout construction.
PORTAGE COUNTY
14
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Portage County Upcoming Projects
Ohio Bridge Partnership Program
Atwater, Rootstown & Randolph Townships
PID: 97402
ESTIMATED CONSTRUCTION COST: $1.2 million
ESTIMATED TOTAL COST: $1.4 million
AWARD DATE: March 2015
COMPLETION DATE: Nov. 2016
PROJECT DESCRIPTION: The replacement of three bridges. Industry Rd. over
Barrel Run between Cook Rd. and Giddings Rd., Stroup Rd. over an unnamed
stream between US 224 and Mott Rd. and Johnny Cake Rd. over Feeder Canal
Tributary between Hartville Rd. and Saxe Rd.
MAINTENANCE OF TRAFFIC: Industry Rd. and Stroup Rd. will be closed for
28 days each. Johnny Cake Rd. will be closed for 60 days. All detours will be
posted. Access to all residences and businesses will be maintained at all times
throughout construction.
Ohio Bridge Partnership Program
City of Kent, Village of Mantua & Hiram Township
PID: 97404
ESTIMATED CONSTRUCTION COST: $1 million
ESTIMATED TOTAL COST: $1.2 million
AWARD DATE: Nov. 2015
COMPLETION DATE: Dec. 2016
PROJECT DESCRIPTION: The replacement of three bridges. Norton Rd. over
Silver Creek between SR 700 and SR 88, Canada Rd. over the Cuyahoga River
between SR 44 and Peck Rd. and Allen Dr. over Fish Creek between Erin Dr. and
Verona Ave.
MAINTENANCE OF TRAFFIC: Norton Rd. and Canada Rd. will be closed for 30
days each. Allen Drive will be closed for 60 days. All detours will be posted.
Access to all residences and businesses will be maintained at all times throughout
construction.
State Route 303
Shalersville & Freedom Townships
Interstate 76
Rootstown & Edinburg Townships
PID: 81636
ESTIMATED CONSTRUCTION COST: $4.4 million
ESTIMATED TOTAL COST: $4.4 million
AWARD DATE: March 2015
COMPLETION DATE: May 2016
PROJECT DESCRIPTION: Resurfacing of I-76 from just east of SR 44 to just east
of SR 14. The project also includes miscellaneous bridge repairs.
MAINTENANCE OF TRAFFIC: Two lanes of traffic will be maintained in each
direction on I-76 during peak traffic hours. A minimum of one lane of traffic will
be maintained in each direction during non-peak traffic hours.
PORTAGE COUNTY
PID: 86932
ESTIMATED CONSTRUCTION COST: $1 million
ESTIMATED TOTAL COST: $1.1 million
AWARD DATE: April 2015
COMPLETION DATE: Sept. 2015
PROJECT DESCRIPTION: Resurfacing of SR 303 between SR 44 and SR 700.
The project also includes the replacement of the bridge on SR 303 between Cooley
Rd. and Limerridge Rd.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers. SR 303 will be closed for 28 days. A detour will be posted.
Access to all residences and businesses will be maintained at all times throughout
construction.
15
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Portage County Upcoming Projects Continued
State Route 14
*
Ravenna Township
PID: 78278
ESTIMATED CONSTRUCTION COST: $4.8 million
ESTIMATED TOTAL COST: $7.5 million
AWARD DATE: May 2015
COMPLETION DATE: Sept. 2016
PROJECT DESCRIPTION: Eliminate fifth leg at the SR 14/SR 59 and Newton
Falls Rd. Intersection. Project will terminate Newton Falls Rd. at Woodbine Ave.
and extend Peck Rd. to SR 59. The project also includes the resurfacing of SR 59
from the Ravenna Corporation limit to SR 5 and the widening of SR 14 between
SR 59 and SR 5.
MAINTENANCE OF TRAFFIC: SR 59 westbound will be closed for 120 days.
SR 14 will have a minimum of one lane of traffic maintained in each direction.
Peck Rd. and Woodbine Ave. will each be closed for 14 days. All detours will be
posted. Access to all residences and businesses will be maintained at all times
throughout construction.
PORTAGE COUNTY
16
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Stark County
Construction Costs:
Active: $8.9 million
Upcoming: $11.8 million
Total: $20.7 million
STARK COUNTY
17
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Stark County Active Projects
State Route 800
Navarre Rd. SW
Canton Township
City of Canton
PID: 76439
CONSTRUCTION COST: $6.2 million
START DATE: December 2014
PID: 76007
CONSTRUCTION COST: $1.4 million
START DATE: December 2014
PROJECT: 14-8012
TOTAL COST: $1.4 million
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Upgrade traffic signals along 14 intersections on
Navarre Rd. SW from Harrison Ave. SW to Market Ave. SW, on 15th St. from
Harrison Ave. SW to Cleveland Ave. SW and on Cleveland Ave. SW from Market
Ave. to 9th St.
MAINTENANCE OF TRAFFIC: A minimum of one lane will be maintained with
flaggers during construction.
*
PROJECT: 14-0420
TOTAL COST: $8.3 million
COMPLETION DATE: Sept. 2016
PROJECT DESCRIPTION: Widening of SR 800 from 33rd St. to 43rd St. to
include turn lanes. Project also includes access management to improve side street
identification and driveway definition.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained in each
direction on SR 800 and Faircrest St. Various 30 day side street closures will occur
throughout the project. All detours will be posted. Access to all residences and
businesses will be maintained at all times throughout construction.
State Route 241
City of Massillon & Tuscarawas Township
PID: 82927
CONSTRUCTION COST: $1.3 million
START DATE: November 2014
PROJECT: 14-8021
TOTAL COST: $1.3 million
COMPLETION DATE: July 2015
PROJECT DESCRIPTION: Resurfacing of SR 241 from SR 93 to SR 21. The
project also includes repairs to three bridges.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained by
flaggers throughout construction.
STARK COUNTY
18
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Stark County Upcoming Projects
Various Routes
Cities of Massillon & Canton; Canton & Sugar Creek Townships
PID: 92444
ESTIMATED CONSTRUCTION COST: $600,000
ESTIMATED TOTAL COST: $600,000
AWARD DATE: March 2015
COMPLETION DATE: Sept. 2015
PROJECT DESCRIPTION: Resurfacing of SR 172 from 3rd St. to 17th St. Project
also includes bridge repairs to the bridge on SR 172 over the Tuscarawas River
between Pine St. and Hess Blvd., on SR 212 over a branch of Sugar Creek between
Dolphin St. and Bellway Ave., on SR 627 just west of I-77 and on SR 800 over a
branch of the Nimishillen Creek between 30th St. and 32nd St.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers throughout construction.
US Route 30
Stark County Culvert Replacements
Various locations
PID: 95248
ESTIMATED CONSTRUCTION COST: $600,000
ESTIMATED TOTAL COST: $800,000
AWARD DATE: May 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Culvert replacements on various routes throughout
Stark County including: one on SR 43 at State St., one on SR 172 between Fox
Ave., and Whitacre Ave., two on SR 183, one between Cenfield St. and Bayton St.
and one just north of Greenbower St. and one culvert on SR 212 between Shetler
Ave. and Parrot Rd.
MAINTENANCE OF TRAFFIC: Traffic will be detoured for each culvert
replacement. Detours will be posted. At all other times, a minimum of one lane of
traffic will be maintained. Access to all residences and businesses will be
maintained at all times throughout construction.
US Route 30 & State Route 93
Sugar Creek, Tuscarawas & Perry Townships; City of Massillon
Village of East Canton; Canton & Osnaburg Townships
PID: 88907
ESTIMATED CONSTRUCTION COST: $700,000
ESTIMATED TOTAL COST: $700,000
AWARD DATE: July 2015
COMPLETION DATE: Dec. 2015
PROJECT DESCRIPTION: Resurfacing of US 30 from Trump Ave. to the
southern East Canton Corporation limit.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers at all times throughout construction.
PID: 86934
ESTIMATED CONSTRUCTION COST: $1.6 million
ESTIMATED TOTAL COST: $1.6 million
AWARD DATE: April 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Replacing median catch basin on US 30 from just east
of the Wayne County line to Whipple Ave. The project also includes resurfacing
on SR 93 from northern Village of Brewster limit to SR 172. The project also
includes miscellaneous bridge repairs and radius improvements at the SR 93 and
Elton St. intersection.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained at all times by flaggers throughout construction.
STARK COUNTY
19
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Stark County Upcoming Projects Continued
US Route 30
City of Canton
Ohio Bridge Partnership Program
Lexington, Sandy & Jackson Townships
PID: 97411
ESTIMATED CONSTRUCTION COST: $1.5 million
ESTIMATED TOTAL COST: $1.8 million
AWARD DATE: March 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: The replacement of the Aebi Ave. bridge over Beech
Creek between Vine St. and SR 619, the High Mill Ave. bridge over Mudbrook
Creek between Fulton Dr. and Portage St. and the Elson St. bridge over Little
Sandy Creek between SR 44 and Brookford Ave.
MAINTENANCE OF TRAFFIC: Aebi Ave. and Elson St. will be closed for 75
days each. High Mill Ave. will be closed for 28 days. All detours will be posted.
Access to all residences and businesses will be maintained at all times throughout
construction.
Ohio Bridge Partnership Program
Cities of North Canton & Massillon; Paris Township
PID: 97410
ESTIMATED CONSTRUCTION COST: $1.3 million
ESTIMATED TOTAL COST: $1.6 million
AWARD DATE: November 2015
COMPLETION DATE: Dec. 2016
PROJECT DESCRIPTION: The replacement of the Freed St. bridge over Hugle
Run between Baird Ave. and Fax Ave., the Easthill St. bridge over Nimishillen
Creek just east of Main St., and 17th St. over Sippo Creek just south of Hankins Rd.
PID: 99566
ESTIMATED CONSTRUCTION COST: $100,000
ESTIMATED TOTAL COST: $100,000
AWARD DATE: July 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Structural repairs to the US 30 westbound ramp bridge
to I-77 northbound. Project includes repairs to abutment joints, piers and
abutments.
MAINTENANCE OF TRAFFIC: The ramp from US 30 westbound to I-77
northbound will be closed for 70 days. A detour will be posted. Access to all
residence and businesses will be maintained at all times throughout construction.
State Routes 43 & 619
Plain, Lake & Marlboro Townships; Village of Hartville
PID: 86933
ESTIMATED CONSTRUCTION COST: $3.1 million
ESTIMATED TOTAL COST: $3.1 million
AWARD DATE: April 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Resurfacing of SR 43 between Applegrove St. to SR
619 and the resurfacing of SR 619 from SR 43 to just west of SR 44.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained at all times by flaggers throughout construction.
MAINTENANCE OF TRAFFIC: Freed St. will be closed for 75 days. Easthill St.
and 17th St. will be closed for 60 days each. All detours will be posted. Access to
all residences and businesses will be maintained at all times throughout
construction.
STARK COUNTY
20
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Stark County Upcoming Projects Continued
State Route 627
Perry & Canton Townships
State Route 183
Sandy Township; Villages of Magnolia and Waynesburg
PID: 86945
ESTIMATED CONSTRUCTION COST: $900,000
ESTIMATED TOTAL COST: $900,000
AWARD DATE: April 2015
COMPLETION DATE: Sept. 2015
PROJECT DESCRIPTION: Resurfacing of SR 183 from the Carroll County line to
Minerva Rd. Project also includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained at all times by flaggers throughout construction.
STARK COUNTY
PID: 86936
ESTIMATED CONSTRUCTION COST: $1.4 million
ESTIMATED TOTAL COST: $1.4 million
AWARD DATE: April 2015
COMPLETION DATE: Sept. 2015
PROJECT DESCRIPTION: Resurfacing of SR 627 from just south of US Route
30 to I-77. The project also includes a concrete overlay to the SR 627 bridge over
I-77.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained at all times by flaggers throughout construction.
21
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Summit County
Upcoming: $64.7 million
Construction Costs:
Active: $104.3 million
Total: $169 million
22
SUMMIT COUNTY
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Summit County Active Projects
31st Street
City of Barberton
Akron Cleveland Road
Village of Boston Heights
PID: 86154
CONSTRUCTION COST: $1.7 million
START DATE: June 2014
PROJECT: 14-0227
TOTAL COST: $3.1 million
COMPLETION DATE: July 2015
PROJECT DESCRIPTION: Replace bridge on Akron Cleveland Rd. over the
Metro Parks trail between SR 303 and W. Barlow Rd. Work that was completed in
2014 included drainage repairs, completion of southbound side of structure. Work
in 2015 includes completion of northbound side structure and asphalt paving of
bridge.
MAINTENANCE OF TRAFFIC: Akron Cleveland Rd. is reduced to one lane of
traffic in each direction.
PID: 86923
CONSTRUCTION COST: $2.6 million
START DATE: November 2014
PROJECT DESCRIPTION: Widening of 31st St. from Wooster Rd. to Shannon
Ave. for the addition of a two way left turn lane. Project also includes signal
upgrades at the Shannon Ave. intersection.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained in each
direction on 31st St. Various 30 day side street closures will occur throughout the
project. All detours will be posted. Access to all residences and businesses will be
maintained at all times throughout construction.
State Route 261
State Road
Cities of Akron & Tallmadge
City of Cuyahoga Falls
PID: 96672
CONSTRUCTION COST: $500,000
START DATE: March 2015
PID: 81605
CONSTRUCTION COST: $8.3 million
START DATE: April 2013
PROJECT: 13-8008
TOTAL COST: $9.2 million
COMPLETION DATE: August 2015
PROJECT DESCRIPTION: Widening of State Rd. from Bath Rd. to Steels
Corners Rd. Project also includes the addition of turn lanes, drainage and signal
improvements. Work completed in 2014 included the widening of the roadway
between Cochran Rd. and Graham Rd. and drainage repairs. Work to be completed
in 2015 includes the widening of the west side of the roadway between Cochran
Rd. and Steels Corners Rd. and the asphalt paving throughout project limits.
PROJECT: 14-0226
TOTAL COST: $3.6 million
COMPLETION DATE: Sept. 2015
*
PROJECT: 14-0470
TOTAL COST: $500,000
COMPLETION DATE: July 2015
PROJECT DESCRIPTION: Resurfacing of SR 261 from Brittain Rd. to the
Tallmadge Circle.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained in each
direction throughout construction except for four nights when SR 261 between
Wright Rd. and the Tallmadge Circle will be closed. A detour will be posted.
Access to all residences and businesses will be maintained throughout
construction.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on State Rd. except for brief periods where one lane
of traffic will be maintained by flaggers.
SUMMIT COUNTY
23
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Summit County Active Projects Continued
Interstate 271
City of Macedonia
Interstate 271
Village of Richfield; Richfield Township
PID: 18710
PROJECT: 13-0147
CONSTRUCTION COST: $46.7 million TOTAL COST: $49.8 million
START DATE: October 2013
COMPLETION DATE: July 2017
PROJECT DESCRIPTION: Pavement replacement of I-271 from Broadview Rd.
to the Ohio Turnpike. Project also includes repairs to nine bridges including two
bridges over I-77, SR 303 over I-271, SR 176 over I-271, Brecksville Rd. over I271 and various ramps at the I-77/I-271 interchange. Work completed in 2014
included the reconstruction of the southbound lanes of I-271 from just east of I-77
to the Ohio Turnpike and the rehabilitation of three overhead bridges, Broadview
Rd., Brecksville Rd., and SR 303 over I-271. Work to be completed in 2015
includes the reconstruction of the northbound lanes of I-271 from just east of I-77
to the Ohio Turnpike and the reconstruction of the bridge on I-271 over I-77
northbound and the reconstruction of the ramp from I-271 northbound to I-77
northbound.
PID: 89458
CONSTRUCTION COST: $44.5 million
START DATE: October 2014
PROJECT: 14-3005
TOTAL COST: $48.1 million
COMPLETION DATE: October 2016
PROJECT DESCRIPTION: Widening of I-271 from just north of SR 8 to the
Cuyahoga County line. Project also includes the widening of four bridges on I-271.
Work completed in 2014 included the partial demolition of structures on I-271
over SR 82, Ledge Rd. and Freeway Drive and the removal of the interior portion
of I-271. Work to be completed in 2015 includes the widening of the interior lanes
of I-271, the partial construction of the bridges on I-271 over SR 82, Ledge Rd.
and Freeway Dr. and the construction of the new ramp from Freeway Drive to I271 northbound.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained on I-271 throughout construction. Short term ramp closures will occur.
All detours will be posted. Access to all residences and businesses will be
maintained throughout construction.
MAINTENANCE OF TRAFFIC: A minimum of two lanes of traffic will be
maintained on I-271 during peak traffic times through a contraflow traffic pattern.
The ramp from I-271 northbound to I-77 northbound will be closed for 90 days.
The ramp from I-77 northbound to I-271 northbound will be closed for 7 days.
Access to all residences and businesses will be maintained at all times throughout
construction.
SUMMIT COUNTY
24
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Summit County Upcoming Projects
State Route 18
*
Bath & Copley Township; City of Fairlawn
Hopocan Ave.
City of Barberton
PID: 98364
ESTIMATED CONSTRUCTION COST: $500,000
ESTIMATED TOTAL COST: $500,000
AWARD DATE: February 2015
COMPLETION DATE: July 2015
PROJECT DESCRIPTION: Resurfacing of Hopocan Ave. from 8th St. to Wooster
Ave.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained with flaggers during construction.
Wooster Rd.
City of Barberton
PID: 98365
ESTIMATED CONSTRUCTION COST: $600,000
ESTIMATED TOTAL COST: $600,000
AWARD DATE: June 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Resurfacing of Wooster Rd. from Hopocan Ave. to
Norton Ave.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained with flaggers during construction.
PID: 83067
ESTIMATED CONSTRUCTION COST: $8.1million
ESTIMATED TOTAL COST: $9.4 million
AWARD DATE: June 2015
COMPLETION DATE: October 2016
PROJECT DESCRIPTION: Widening of SR 18 between S. Hametown Rd. and I77. The project also includes the relocation of the SR 18 eastbound entrance ramp
to I-77 southbound, the replacement of the SR 18 bridge over Yellow Creek
between Creekrun Drive and Harmony Hills Rd. and the resurfacing of SR 18
between the Medina County line and Western Akron corporation limit.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 18 during non-peak travel times. SR 18
between Creekrun Rd. and Harmony Hills Dr. will be reduced to one lane in each
direction during the bridge replacement. Various short term ramp closures will
occur at the I-77/SR 18 interchange. All detours will be posted. Access to all
residences and businesses will be maintained at all times throughout construction.
State Route 18/Brittain Rd.
City of Akron
PID: 86996
ESTIMATED CONSTRUCTION COST: $1.6 million
ESTIMATED TOTAL COST: $2 million
AWARD DATE: January 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Replacement of the Brittain Rd. bridge over SR 18/E.
Market St. between Massillon Rd. and Seiberling St.
MAINTENANCE OF TRAFFIC: Brittain Rd. will be closed for 120 days. A
detour will be posted. Access to all residences and businesses will be maintained at
all times throughout construction.
SUMMIT COUNTY
25
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Summit County Upcoming Projects Continued
Interstate 76
City of Akron
State Routes 21, 176 & 303
Village of Richfield; Richfield and Boston Townships
PID: 88911
ESTIMATED CONSTRUCTION COST: $2.7 million
ESTIMATED TOTAL COST: $2.7 million
AWARD DATE: May 2015
COMPLETION DATE: Sept. 2015
PID: 77876
ESTIMATED CONSTRUCTION COST: $6.7 million
ESTIMATED TOTAL COST: $6.7 million
AWARD DATE: October 2015
COMPLETION DATE: August. 2016
PROJECT DESCRIPTION: Concrete pavement repairs between Inman St. and
Gilchrist Rd. The project also includes multiple bridge overlays.
PROJECT DESCRIPTION: Resurfacing of SR 176 from just west of I-77 to the
Cuyahoga County line and on SR 303 from the Medina County line to the Village
of Peninsula western corporation limit. The project also includes drainage repairs
to SR 21 between the Ohio Turnpike and Cuyahoga County line.
MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times. A
minimum of one lane of traffic will be maintained in each direction on I-76 during
non-peak travel times.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained at all times by flaggers throughout construction.
Interstates 76/77 Kenmore Leg
*
City of Akron
Interstate 76/77
City of Akron; Coventry Township
PID: 98061
ESTIMATED CONSTRUCTION COST: $2 million
ESTIMATED TOTAL COST: $2.2 million
AWARD DATE: January 2015
COMPLETION DATE: Sept. 2016
PROJECT DESCRIPTION: Widening and re-decking of the I-77 northbound ramp
bridge to I-277 westbound. The project also includes a deck replacement on the
Chester Ave. pedestrian bridge over I-76.
MAINTENANCE OF TRAFFIC: The ramp from I-77 northbound to I-277
westbound will be closed for 60 days after August 10, 2015. Pedestrian traffic over
I-76 will be detoured for 45 days. All detours will be posted. Access to all
residences and businesses will be maintained at all times throughout construction.
SUMMIT COUNTY
PID: 84655
ESTIMATED CONSTRUCTION COST: $8.5 million
ESTIMATED TOTAL COST: $8.5 million
AWARD DATE: March 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Resurfacing of I-76/Kenmore Leg from I-277 to I-77.
The project also includes shoulder replacements on I-77 southbound between
Killian Rd. to I-277, I-77 northbound between SR 261 and SR 162 and on I-277
between I-76 and just west of SR 93/Manchester Rd. Also included in this project
is the widening of the I-277 eastbound to I-77 southbound ramp.
MAINTENANCE OF TRAFFIC: I-76 eastbound and westbound will be closed for
a maximum of 75 days. I-76 westbound will be closed first. All lanes will be reopened by July 31, 2015. All detours will be posted. Access to all residences and
businesses will be maintained at all times throughout construction
26
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Summit County Upcoming Projects Continued
State Route 82
Interstate 77
City of Macedonia
City of Green; Coventry Township
PID: 81656
ESTIMATED CONSTRUCTION COST: $4.1 million
ESTIMATED TOTAL COST: $5.6 million
AWARD DATE: January 2015
COMPLETION DATE: October 2016
PID: 76391
ESTIMATED CONSTRUCTION COST: $4 million
ESTIMATED TOTAL COST: $4 million
AWARD DATE: October 2015
COMPLETION DATE: Nov. 2016
PROJECT DESCRIPTION: Resurfacing of I-77 from SR 241 to Killian Rd. The
project also includes miscellaneous bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on I-77 during non-peak travel times. The ramps at
Arlington Rd. will be closed for two consecutive nights. All detours will be posted.
Access to all residences and businesses will be maintained at all times throughout
construction.
PROJECT DESCRIPTION: Widening of SR 82 between Shepard Rd. and Crow
Dr. Project also includes the addition of bike lanes on SR 82.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 82. Shepard Rd. will be closed for 60 days on
each side of SR 82. These closures will not occur at the same time. All detours will
be posted. Access to all residences and businesses will be maintained at all times
throughout construction.
State Routes 8/82
Interstates 76/77 Spicer/Johnston Bridges
*
City of Akron
PID: 86979
ESTIMATED CONSTRUCTION COST: $15.4 million
ESTIMATED TOTAL COST: $19.9 million
AWARD DATE: February 2015
COMPLETION DATE: July 2017
PROJECT DESCRIPTION: Removal of three bridges on I-76/I-77 over Johnston
St. Project also includes the relocation of Johnston St. between Spicer St. and
Brown St.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on I-76/I-77 during non-peak hours. Johnston St. will
be closed for 240 days. Brown St. will be closed for 60 days. All detours will be
posted. Access to all residences and businesses will be maintained at all times
throughout construction.
SUMMIT COUNTY
*
*
Village of Northfield; Northfield Center Township
PID: 84563
ESTIMATED CONSTRUCTION COST: $2.7 million
ESTIMATED TOTAL COST: $2.8 million
AWARD DATE: March 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Resurfacing of SR 82 from the Cuyahoga County line
to Summer Rd., just west of I-271. Project also includes the widening of SR 82
between Holzhauer Rd. to Boyden St. and the installation of curb ramps on SR 8
from the southern Northfield corporation limit to the Cuyahoga County line.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 82 except for two nights when SR 82 will be
closed. A minimum of one lane of traffic will be maintained by flaggers on SR 8.
27
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Summit County Upcoming Projects Continued
State Route 303
Village of Boston Heights
State Routes 82/91 & Interstate 480
City of Twinsburg; Twinsburg Township
PID: 86954
ESTIMATED CONSTRUCTION COST: $2.1 million
ESTIMATED TOTAL COST: $2.1 million
AWARD DATE: April 2015
COMPLETION DATE: Sept. 2015
PROJECT DESCRIPTION: Resurfacing of the ramps at I-480 and SR 91, SR 82
from I-480 to Ravenna Rd. and SR 91 from the southern Twinsburg corporation
limit to Post Rd. The project also includes minor bridge repairs.
PID: 94493
ESTIMATED CONSTRUCTION COST: $1.6 million
ESTIMATED TOTAL COST: $1.8 million
AWARD DATE: October 2015
COMPLETION DATE: October 2016
PROJECT DESCRIPTION: Redecking and painting of the SR 303 bridge over the
Hike and Bike Trail just west of Olde Route 8.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 303 throughout construction.
MAINTENANCE OF TRAFFIC: A minimum of one lane will be maintained by
flaggers during construction.
State Route 91
*
City of Twinsburg
PID: 85078
ESTIMATED CONSTRUCTION COST: $4.1 million
ESTIMATED TOTAL COST: $5.4 million
AWARD DATE: April 2015
COMPLETION DATE: August 2016
PROJECT DESCRIPTION: Widening and reconstruction of SR 91 between Post
Rd. and Glenwood Dr. The project also includes drainage repairs and the
installation of a roundabout on SR 91 and Glenwood Dr.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on SR 91. Glenwood Dr. will be closed for 60 days on
each side of SR 91. All detours will be posted. Access to all residences and
businesses will be maintained at all times throughout construction.
SUMMIT COUNTY
28
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Trumbull County
Upcoming: $32.5 million
Construction Costs:
Active: $26 million
Total: $58.5 million
29
TRUMBULL COUNTY
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Trumbull County Active Projects
State Routes 5, 7 & 87
Greene, Gustavus, Hartford & Kinsman Townships
High Street & Main Street
City of Cortland
PID: 84621
CONSTRUCTION COST: $1.4 million
START DATE: August 2014
PROJECT: 14-0327
TOTAL COST: $2 million
COMPLETION DATE: August 2015
PROJECT DESCRIPTION: Replacement of the Main St. bridge between High St.
and Walnut St. Project also includes the addition of a left turn lane at E. Main St.
and N. High St. Work completed in 2014 included the replacement of the Main St.
bridge between High St. and Walnut St. Work to be completed in 2015 includes the
widening of High St. and asphalt paving of the entire project.
MAINTENANCE OF TRAFFIC: Traffic will be maintained with flaggers at all
times throughout construction.
PID: 86939
CONSTRUCTION COST: $4 million
START DATE: November 2014
PROJECT: 14-0446
TOTAL COST: $4 million
COMPLETION DATE: Sept. 2014
PROJECT DESCRIPTION: Resurfacing of SR 5 from SR 7 to the Pennsylvania
state line, resurfacing of SR 7 from SR 305 to Bradley Brownlee Rd., and the
resurfacing of SR 87 from SR 46 to SR 7. The project includes miscellaneous
bridge repairs including patching and overlays to six structures.
MAINTENANCE OF TRAFFIC: One lane of traffic will be maintained by
flaggers at all times throughout construction. SR 7, SR 87 and SR 193 and will be
closed for five days. A detour will be posted. Access to all residences and
businesses will be maintained throughout construction.
State Routes 5/82 (Warren Bypass)
Olive St.
Warren, Champion, Bazetta & Howland Townships
Village of McDonald; City of Niles
PID: 82420
CONSTRUCTION COST: $3.7 million
START DATE: April 2014
PROJECT: 13-0613
TOTAL COST: $4.9 million
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Replacement of a bridge on Olive St. over the
Mahoning River and B&O Railroad between Summit Ave. and Ohio Ave. Work
completed in 2014 included demolition of the old structure and construction of
abutments and bridge piers. Work to be completed in 2015 includes construction of
the new bridge and drainage repairs.
PID: 96890
CONSTRUCTION COST: $1.2 million
START DATE: March 2015
14-0447
TOTAL COST: $1.2 million
COMPLETION DATE: June 2015
PROJECT DESCRIPTION: Installation of cable median rail along SR 5/82
(Warren Bypass) from SR 5 to E. Market St.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction of SR 5/82 (Warren Bypass) during non-peak travel
times throughout construction.
MAINTENANCE OF TRAFFIC: Olive St. is currently closed and will remain
closed throughout the project. A detour is posted. Access to all residences and
businesses will be maintained at all times throughout construction.
TRUMBULL COUNTY
30
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Trumbull County Active Projects Continued
US Route 422
City of Warren
State Routes 46 & 169
City of Niles; Howland Township
PID: 86959
CONSTRUCTION COST: $600,000
START DATE: March 2015
PROJECT:14-0421
TOTAL COST: $600,000
COMPLETION DATE: August 2015
PROJECT DESCRIPTION: Resurfacing of SR 46 from US 422 to Niles Vienna
Rd. and the resurfacing of SR 169 from SR 46 to State Rd. and from SR 46 to
Cleveland Ave.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers during construction.
PID: 83629
CONSTRUCTION COST: $3.3 million
START DATE: November 2014
PROJECT: 14-0358
TOTAL COST: $4.3 million
COMPLETION DATE: August 2015
PROJECT DESCRIPTION: Installation of a two way left turn lane and resurfacing
on US 422 in the City of Warren between Southern Blvd. and Linda Dr. Project
also includes the installation of a left turn storage lane at US 422 and Coit Rd. as
well as a new storm system, curb, sidewalks and traffic signals.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained in each direction on US 422. Coit Rd. and Southern Blvd. will be
closed for 30 days. All detours will be posted. Access to all residences and
businesses will be maintained throughout construction.
Interstate 80
Hubbard Township
PID: 81510
PROJECT: 13-0567
CONSTRUCTION COST: $11.8 million TOTAL COST: $13.2 million
START DATE: April 2014
COMPLETION DATE: October 2016
PROJECT DESCRIPTION: The replacement of two bridges on I-80 over Mt.
Everett Rd. Project also includes the realignment of Mt. Everett Rd. under I-80.
Work completed in 2014 included the construction of the southern half of the
westbound bridge. Work to be completed in 2015 includes construction of the
northern half of the westbound bridge and construction of a portion of the
eastbound bridge.
MAINTENANCE OF TRAFFIC: Two lanes of traffic will be maintained in each
direction of I-80 during peak traffic hours. A minimum of one lane of traffic will
be maintained in each direction during non-peak traffic hours. Mt. Everett Rd. will
be closed throughout the duration of the project. A detour will be posted. Access to
all residences and businesses will be maintained at all times throughout
construction.
TRUMBULL COUNTY
31
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Trumbull County Upcoming Projects
Chestnut Ridge Rd.
Hubbard Township
PID: 84458
ESTIMATED CONSTRUCTION COST: $800,000
ESTIMATED TOTAL COST: $1.2 million
AWARD DATE: May 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Replacement of the Chestnut Ridge Rd. bridge over
Little Yankee Run between Hubbard Masury Rd. and the Pennsylvania State line.
Project also includes intersection improvements to Chestnut Ridge Rd. and Fox
North Rd.
MAINTENANCE OF TRAFFIC: Chestnut Ridge Rd. will be closed for a period of
120 days. A detour will be posted. At all other times a minimum of one lane of
traffic will be maintained by flaggers during construction. Access to all residences
and businesses will be maintained at all times throughout construction.
Trumbull County Culvert Replacements
Various locations
PID: 95250
ESTIMATED CONSTRUCTION COST: $400,000
ESTIMATED TOTAL COST: $500,000
AWARD DATE: May 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Culvert replacements on various routes throughout
Trumbull County including: one on SR 5 between Dell Thomas Rd. and Ward
North Rd., one on SR 88 just west of SR 45 and one on SR 305 between Bell South
Rd. and SR 193.
MAINTENANCE OF TRAFFIC: Traffic will be detoured for each culvert
replacement. Detours will be posted. At all other times, a minimum of one lane of
traffic will be maintained. Access to all residences and businesses will be
maintained at all times throughout construction.
Messick South Rd.
Bristol Township
King Graves Rd.
Vienna Township
PID: 97953
ESTIMATED CONSTRUCTION COST: $700,000
ESTIMATED TOTAL COST: $700,000
AWARD DATE: April 2015
COMPLETION DATE: Nov. 2015
PROJECT DESCRIPTION: Resurfacing of King Graves Rd. between SR 11 and
SR 193.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers throughout construction.
TRUMBULL COUNTY
PID: 84463
ESTIMATED CONSTRUCTION COST: $500,000
ESTIMATED TOTAL COST: $700,000
AWARD DATE: March 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Replacement of the Messick South Rd. bridge over
Baughman Creek just south of Peck Leach Rd.
MAINTENANCE OF TRAFFIC: Messick South Rd. will be closed for a period of
90 days. A detour will be posted. At all other times a minimum of one lane of
traffic will be maintained by flaggers during construction. Access to all residences
and businesses will be maintained at all times throughout construction.
32
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Trumbull County Upcoming Projects Continued
Newton Falls Bailey Rd.
Village of Lordstown
PID: 84461
ESTIMATED CONSTRUCTION COST: $1.1 million
ESTIMATED TOTAL COST: $1.4 million
AWARD DATE: March 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Replacement of the Newton Falls Bailey Rd. bridge
over Duck Creek between Layer Rd. and Wood Lenhart Rd. The project also
includes roadway reconstruction and realignment.
MAINTENANCE OF TRAFFIC: Newton Falls Bailey Rd. will be closed for a
period of 120 days. A detour will be posted. At all other times a minimum of one
lane of traffic will be maintained by flaggers during construction. Access to all
residences and businesses will be maintained at all times throughout construction.
Palmyra Rd.
Warren Township
PID: 84459
ESTIMATED CONSTRUCTION COST: $600,000
ESTIMATED TOTAL COST: $900,000
AWARD DATE: May 2015
COMPLETION DATE: Dec. 2015
PROJECT DESCRIPTION: Replacement of the bridge on Palmyra Rd. over Little
Duck Creek between Hewitt Gifford Rd. and Kibler Toot Rd. with a box culvert.
MAINTENANCE OF TRAFFIC: Palmyra Rd. will be closed for a period of 120
days. A detour will be posted. At all other times a minimum of one lane of traffic
will be maintained by flaggers during construction. Access to all residences and
businesses will be maintained at all times throughout construction.
TRUMBULL COUNTY
Ohio Bridge Partnership Program
Bristol & Gustavus Townships
PID: 97420
ESTIMATED CONSTRUCTION COST: $700,000
ESTIMATED TOTAL COST: $900,000
AWARD DATE: March 2015
COMPLETION DATE: October 2016
PROJECT DESCRIPTION: The replacement of the Fenton Rd. bridge over
Baughman Creek between Messick South Rd. and Nurse East Rd. and the Barclay
North Rd. bridge over an unnamed stream between Wakefield Creek Rd. and
Kinsman Rd.
MAINTENANCE OF TRAFFIC: Fenton Rd. will be closed for 75 days. Barclay
North Rd. will be closed for 28 days. All detours will be posted. Access to all
residences and businesses will be maintained at all times throughout construction.
Ohio Bridge Partnership Program
Vienna & Warren Townships
PID: 97418
ESTIMATED CONSTRUCTION COST: $1.3 million
ESTIMATED TOTAL COST: $1.6 million
AWARD DATE: November 2015
COMPLETION DATE: June 2017
PROJECT DESCRIPTION: The replacement of the Niles Vienna Rd. bridge over
Liberty Lake stream between Smith Stewart Rd. and Scoville North Rd., the Risher
Rd. bridge over Duck Creek just west of S. Leavitt Rd. and the Pleasant Valley Rd.
bridge over Squaw Creek just south of Smith-Stewart Rd.
MAINTENANCE OF TRAFFIC: Niles Vienna Rd., Risher Rd. and Pleasant
Valley Rd. will be closed for 75 days. All detours will be posted. Access to all
residences and businesses will be maintained at all times throughout construction.
33
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Trumbull County Upcoming Projects Continued
State Route 11
Howland & Liberty Townships
State Route 5
*
Warren Township
PID: 91350
ESTIMATED CONSTRUCTION COST: $5.7 million
ESTIMATED TOTAL COST: $6.3 million
AWARD DATE: February 2015
COMPLETION DATE: Oct. 2015
PROJECT DESCRIPTION: Rehabilitation to three bridge structures on SR 5, one
on Market St. over SR 5, one Eagle Creek Rd. over SR 5 and one on N. Leavitt Rd.
over SR 5.
MAINTENANCE OF TRAFFIC: Market St. will be closed for 180 days. Eagle
Creek Rd. will be closed for 60 days. N. Leavitt Rd. will be closed for 90 days. The
ramp from US 422 to SR 5 westbound will be closed for 90 days. Traffic on SR 5
will be maintained at all times. All detours will be posted. Access to all residences
and businesses will be maintained at all times throughout construction.
PID: 76408
ESTIMATED CONSTRUCTION COST: $6.6 million
ESTIMATED TOTAL COST: $7.4 million
AWARD DATE: October 2015
COMPLETION DATE: Sept. 2017
PROJECT DESCRIPTION: Raising and redecking of four bridges. Tibbetts Wick
Rd. over SR 11, Anderson Morris Rd. over SR 11, SR 304 over SR 11 and Liberty
St. over SR 11.
MAINTENANCE OF TRAFFIC: Liberty Jones Rd. and SR 304 will be closed for
90 days. Anderson Morris Rd. will be closed for 75 days. Tibbetts Wick Rd. will
be reduced to one lane during construction. All detours will be posted. Access to
all residences and businesses will be maintained at all times throughout
construction.
US Route 62
City of Hubbard
State Routes 5, 305 & US Route 62
Braceville, Hubbard, Bazetta &Champion Townships
PID: 93875
ESTIMATED CONSTRUCTION COST: $200,000
ESTIMATED TOTAL COST: $200,000
AWARD DATE: March 2015
COMPLETION DATE: Sept. 2015
PROJECT DESCRIPTION: Signal replacements on SR 5 at SR 534, on US 62 at
Hubbard Masury Rd., and on SR 305 at N. Park Ave.
MAINTENANCE OF TRAFFIC: Traffic will be maintained at all times
throughout construction.
TRUMBULL COUNTY
PID: 88930
ESTIMATED CONSTRUCTION COST: $1.5 million
ESTIMATED TOTAL COST: $1.5 million
AWARD DATE: July 2015
COMPLETION DATE: Dec. 2015
PROJECT DESCRIPTION: Resurfacing of US 62 from the western Hubbard
Corporation limit to the northern Hubbard Corporation limit. The project also
includes minor bridge repairs.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers during construction.
34
2015 DISTRICT 4 CONSTRUCTION PROGRAM
Trumbull County Upcoming Projects Continued
State Route 534
Farmington Township
US Route 62
*
Hubbard & Brookfield Townships
PID: 77886
ESTIMATED CONSTRUCTION COST: $10.5 million
ESTIMATED TOTAL COST: $10.9 million
AWARD DATE: October 2015
COMPLETION DATE: Nov. 2016
PROJECT DESCRIPTION: Resurfacing of US 62 from the northern Hubbard
Corporation limit to the Pennsylvania state line. The project also includes repairs to
five bridges, including the replacement and widening of the I-80 bridges over US
62.
PID: 90188
ESTIMATED CONSTRUCTION COST: $1.5 million
ESTIMATED TOTAL COST: $1.9 million
AWARD DATE: July 2015
COMPLETION DATE: July 2016
PROJECT DESCRIPTION: Replacement of two bridges on SR 534 over the Grand
River, just south of SR 88.
MAINTENANCE OF TRAFFIC: State Route 534 will be closed for 120 days. A
detour will be posted. Access to all residences and businesses will be maintained at
all times throughout construction.
MAINTENANCE OF TRAFFIC: Traffic will be maintained on I-80 and US 62 at
all times throughout construction. Each of the ramps from I-80 to US 62 will be
closed for 60 day. Ramps at the SR 82 and US 62 interchange will be closed for
one weekend. All detours will be posted. Access to all residences and businesses
will be maintained at all times throughout construction.
State Route 304
Liberty Township
PID: 86956
ESTIMATED CONSTRUCTION COST: $300,000
ESTIMATED TOTAL COST: $300,000
AWARD DATE: April 2015
COMPLETION DATE: October 2015
PROJECT DESCRIPTION: Resurfacing of SR 304 from US 422 to the Girard
eastern corporation limit.
MAINTENANCE OF TRAFFIC: A minimum of one lane of traffic will be
maintained by flaggers on SR 304 throughout construction.
TRUMBULL COUNTY
35
OUR MISSION
To provide easy conveyance of people
and goods from place to place, we will:
Take care of what we have;
Make our system work better;
Improve safety;
Enhance capacity
OUR VISION
A long-term, reliable, professional and
highly productive organization
For more information, contact the ODOT District 4 Public Information Office at (330) 786-2208.
Like us on Facebook:
www.facebook.com/ODOTD4
Follow us on Twitter:
www.twitter.com/ODOT_Akron
Statewide Traffic Information:
www.Ohgo.com
For general information, call (330) 786-2230 or visit District 4’s Web site at: www.transportation.ohio.gov/dist4