Bid Letting - Illinois Tollway

Illinois Tollway Projects
Tri-State Tollway (I-294)
Cost Magnitude Key:
A B C D E F UU / SA -
Jane Addams Memorial Tollway (I-90)
Reagan Memorial Tollway (I-88)
Veterans Memorial Tollway (I-355)
Elgin-O'Hare (EO)
Systemwide (S/W)
Other Agency Major Projects
CONSTRUCTION CONTRACT
BID LETTING SCHEDULE
(Sorted by Bid‐Opening)
IDOT
OMP & O'Hare/Midway CIP
$5 - $10M
$10 - $25M
$25 - $50M
$50 - $75M
$75 - $100M
> $100M
$0 - $5M Unbundled
Set Aside for Small Businesses
Located on Illinois Tollway Website under Doing
Business www.illinoistollway.com
CHICAGO AREA MAJOR TRANSPORTATION AGENCIES
Information in this document is subject to change.
ROUTE
TYPE OF WORK
90
Non Roadway
EO
Recon/Widen
90
PROJECT DESCRIPTION
Ramp Queue Detection / DMS
I-90 Irene WB, US 20, I-39 (MP 17.1 - 52.5)
PROJECT NUMBER
ADVERTISE
DATE
BID OPENING
DATE
ESTIMATED
BOARD
APPROVAL
ESTIMATED
NOTICE TO
PROCEED
CONTRACT
COMPLETION
DATE
COST MAGNITUDE (See
key)
4198
18-Sep-14 A
16-Oct-14 A
20-Nov-14 A
11-Feb-15
9-Feb-16
U
Park Blvd-Pierce Rd-Ketter Dr
Reconstruct/Add Lane
4621
17-Sep-14 A
21-Oct-14 A
20-Nov-14 A
6-Feb-15
5-Aug-15
A
Mainline work
Outside Mainline Rdwy and Bridges
Wolf Rd to Mannheim Rd
(MP 75.1 to 76.6)
4211
25-Sep-14 A
30-Oct-14 A
20-Nov-14 A
4-Feb-15
1-Jun-16
D
90
Mainline work
Outside Mainline Rdwy and Bridge
Oakton St to Wolf Rd
(MP 73.3 to 75.1)
4210
29-Sep-14 A
30-Oct-14 A
20-Nov-14 A
4-Feb-15
23-Dec-15
D
90
Mainline work
Outside Rdwy Reconstr. and widening
Roselle Rd to I-290 / IL Rt 53
(MP 65.5 to 68.1)
4207
9-Oct-14 A
13-Nov-14 A
18-Dec-14 A
17-Feb-15
23-Dec-15
D
90
Mainline work
Outside Mainline Rdwy
W of Higgins Rd to Roselle Rd
(MP 60.8 to 65.5)
4206
14-Oct-14 A
13-Nov-14 A
18-Dec-14 A
17-Feb-15
23-Dec-15
D
EO
Miscellaneous
Fabrication of the Joints & Bearings
Lake St (US 20) to Meacham Rd
4643
7-Nov-14 A
2-Dec-14 A
18-Dec-14 A
18-Feb-15
30-Sep-15
U
90
Mainline work
Outside Mainline Rdwy and Bridges
I-290 / IL 53 to Arlington Hts Rd
(MP 68.1 to 70.7)
4208
20-Oct-14 A
4-Dec-14 A
18-Dec-14 A
17-Feb-15
23-Dec-15
D
90
Mainline work
Outside Mainline Rdwy and Bridges
Arlington Hts Rd to East of Oakton St
(MP 70.7 to 73.3)
4209
21-Oct-14 A
4-Dec-14 A
18-Dec-14 A
17-Feb-15
23-Dec-15
D
90
Mainline work
Outside Mainline Rdwy & Bridge Reconstr.
IL Rt 25 to Higgins Rd
(MP 56.8 to 60.8)
4205
7-Nov-14 A
11-Dec-14 A
29-Jan-15 A
6-Mar-15
23-Dec-15
E
S/W
ITS
Systemwide Dynamic Message Signs Upgrade
Non-CRP
9169
7-Nov-14 A
16-Dec-14 A
29-Jan-15 A
26-Mar-15
17-Sep-15
U
90
Mainline work
WB Rdwy & Bridge Reconstr.
IL RT 31 to Fox River
(MP 54.4 to 55.4)
4204
18-Nov-14 A
16-Dec-14 A
29-Jan-15 A
7-Mar-15
23-Dec-15
C
90
Mainline work
EB Mainline Rdwy and Bridge
Mannheim Rd to Kennedy
4212
20-Nov-14 A
18-Dec-14 A
29-Jan-15 A
23-Mar-15
23-Nov-16
D
S/W
Facility
CA Building North Enterance, ADA Ramp and
ADA Parking
9135R
7-Nov-14 A
18-Dec-14 A
29-Jan-15 A
20-Mar-15
28-Aug-15
U
IDOT
Miscellaneous
IDOT Bid Letting
294
Maintenance
Salt Barn Lighting
Maintenance Facility M1 @ I-294
90
Reconstruct
90
19-Dec-14 A
4214
17-Nov-14 A
8-Jan-15 A
29-Jan-15 A
19-Mar-15
10-Jun-15
U/SA
IL 72 (Higgins Rd)
Crossroad Bridge Reconstruction
5698
4-Dec-14 A
8-Jan-15 A
29-Jan-15 A
23-Mar-15
18-Dec-15
A
Miscellaneous
I-90 Various Repairs
(West of Cherry Valley I-39 Int)
MP 0 to 17.2
4175R
11-Dec-14 A
13-Jan-15 A
26-Feb-15
4-May-15
22-Oct-15
U
90
Reconstruct
Garden Prairie and Anthony Rd
Crossroad Bridge Reconstruction
5697
11-Dec-14 A
13-Jan-15 A
26-Feb-15
27-Apr-15
6-Nov-15
A
88
Reconstruct
Roadway Resurface
US 30 to US52
5660
6-Jan-14 A
27-Jan-15 A
26-Feb-15
24-Apr-15
1-Jun-16
D
IDOT
Miscellaneous
IDOT Bid Letting
294
Miscellaneous
Tri-state Roadway Safety and Structural Repairs
(M.P. 23 to 52.8)
5707
12-Jan-15 A
3-Feb-15
26-Feb-15
27-Apr-15
13-Nov-15
A
88
Reconstruct
Roadway Resurface
US 52 to Midway Rd
5661
6-Jan-15 A
3-Feb-15
26-Feb-15
24-Apr-15
1-Jun-16
D
90
Watermain
NSMJAWA Watermain Reloc - Elmhurst Rd
Piping Instl.
4648
6-Jan-15 A
3-Feb-15
26-Feb-15
26-Apr-15
31-May-16
B
90
Interchange
Rdwy, Ramp and Plazas
Barrington Rd
4220
18-Dec-14 A
5-Feb-15
26-Feb-15
27-Apr-15
30-Nov-16
C
294
Maintenance
Demo and Abatement
Maintenance Facility M1 @ I-294
4213
23-Dec-14 A
10-Feb-15
26-Feb-15
23-Apr-15
25-Aug-15
U/SA
88
Reconstruct
5662
26-Jan-15 A
17-Feb-15
26-Feb-15
24-Apr-15
1-Jun-16
C
Roadway Resurface
Midway Rd to IL 251
30-Jan-15 A
Page 1 of 2
Report Run: 1/30/2015
Illinois Tollway Projects
Tri-State Tollway (I-294)
Cost Magnitude Key:
A B C D E F UU / SA -
Jane Addams Memorial Tollway (I-90)
Reagan Memorial Tollway (I-88)
Veterans Memorial Tollway (I-355)
Elgin-O'Hare (EO)
Systemwide (S/W)
Other Agency Major Projects
CONSTRUCTION CONTRACT
BID LETTING SCHEDULE
(Sorted by Bid‐Opening)
IDOT
OMP & O'Hare/Midway CIP
$5 - $10M
$10 - $25M
$25 - $50M
$50 - $75M
$75 - $100M
> $100M
$0 - $5M Unbundled
Set Aside for Small Businesses
Located on Illinois Tollway Website under Doing
Business www.illinoistollway.com
CHICAGO AREA MAJOR TRANSPORTATION AGENCIES
Information in this document is subject to change.
PROJECT DESCRIPTION
PROJECT NUMBER
ADVERTISE
DATE
BID OPENING
DATE
ESTIMATED
BOARD
APPROVAL
ESTIMATED
NOTICE TO
PROCEED
CONTRACT
COMPLETION
DATE
COST MAGNITUDE (See
key)
ROUTE
TYPE OF WORK
S/W
ITS
Systemwide Ramp Count / Type II DMS
Non-Roadway - Non-CRP
9175
20-Jan-15 A
17-Feb-15
26-Mar-15
29-May-15
18-Dec-15
U
90
Interchange
I-90 at Irene Rd
(Ramps T/F the West)
4218
8-Jan-15 A
19-Feb-15
26-Mar-15
22-May-15
29-Dec-15
A
88
Reconstruct
Mitchell Rd over I-88
Bridge Removal and Replacement
MP 118.2
5699
29-Jan-15 A
24-Feb-15
26-Mar-15
1-Jun-15
14-Dec-15
U
S/W
FiberOptics
Systemwide FiberOptic Reloc.
4219R
9-Feb-15
3-Mar-15
26-Mar-15
15-May-15
15-May-17
U
S/W
Facility
CA Improvements
(AS1 Handler, Boiler Replc.)
9174
3-Feb-15
3-Mar-15
26-Mar-15
28-May-15
1-Oct-15
U/SA
IDOT
Miscellaneous
IDOT Bid Letting
294
Maintenance
Boiler Replacements at M-2, M-4, M-5
and M-8
294
Maintenance
EO
Reconstuction
EO
Rehabilitation
294
Maintenance
294
Maintenance
294
Miscellaneous
EO
6-Mar-15
4203
5-Feb-15
10-Mar-15
26-Mar-15
15-May-15
25-Sep-15
U/SA
5702
10-Feb-15
10-Mar-15
26-Mar-15
22-May-15
14-Nov-15
U
Wood Dale Rd bridge Over Elgin O'Hare Tollway
4640
3-Feb-15
10-Mar-15
26-Mar-15
26-May-15
20-Dec-16
B
Lake St (US 20) to Meacham/Medinah Rd
Rehabilitation
4647
11-Feb-15
12-Mar-15
26-Mar-15
26-May-15
30-Nov-15
B
Building and Site Signage
Maintenance Facility M1 @ I-294
4215
13-Feb-15
17-Mar-15
23-Apr-15
18-Jun-15
25-Sep-15
U
Landscaping
Maintenance Facility M1 @ I-294
4217
13-Feb-15
17-Mar-15
23-Apr-15
19-Jun-15
30-Oct-15
U/SA
Cleaning & Sealing Bridge Decks / Pier Caps /
MOT
(MP 9.7 to 16.62)
5706
3-Mar-15
31-Mar-15
23-Apr-15
23-Jun-15
15-Nov-15
U
Demolition
EOWA Building Demolition
4649
2-Mar-15
31-Mar-15
23-Apr-15
26-Jun-15
31-Dec-18
U
S/W
Maitenance
Bridge Cantilever Pier Cap Analysis and
Strengthening
(I-294, I-88, I-90 and I-355)
5708
9-Mar-15
2-Apr-15
23-Apr-15
23-Jun-15
18-Nov-15
U
88
Maintenance
I-88 / I-47 Salt Dome & Disaster recovery Area
Pavement Rprs
5664-3
18-Mar-15
7-Apr-15
23-Apr-15
15-Jun-15
15-Aug-15
U
90
ITS
Smart Corridor / ITS
4227
11-Mar-15
9-Apr-15
23-Apr-15
23-Jun-15
15-Nov-16
B
IDOT
Miscellaneous
IDOT Bid Letting
S/W
Maitenance
Video Surveillance System
UIC Call Center
TBD(5681-1)
5-Mar-15
30-Apr-15
28-May-15
23-Jul-15
31-Dec-15
U
294
Drainage
Drainage Str Clean and Televise
I-294; MP 6.3 to 17.6
TBD(5681-3)
10-Mar-15
30-Apr-15
28-May-15
1-Aug-15
30-Nov-15
U
294
Rehabilitation
Drainage Improvements ‐ Cermak Road
5694
2-Apr-15
30-Apr-15
28-May-15
24-Jul-15
18-Nov-16
U
EO
Reconstruction
Park Bld to Arlington Hts Rd
(Interchange & Retaining/Noise Wall)
4629
23-Mar-15
5-May-15
28-May-15
20-Jul-15
31-Aug-17
D
S/W
Facility
M-14 Truck Scale
TBD(9132-2B)
15-May-15
9-Jun-15
25-Jun-15
27-Aug-15
24-Dec-15
U
EO
Mainline work
Mainline and Interchange
Lively Blvd to IL 83
4644
28-Apr-15
9-Jun-15
25-Jun-15
20-Aug-15
30-Nov-17
C
S/W
Facility
Replace Boiler and HVAC
(Plz - 1,9,24,61 AND 75)
Non-CRP
TBD(9132-12B)
11-Jun-15
9-Jul-15
23-Jul-15
24-Sep-15
4-Jan-16
U
Clean and Televise Drainage Str. @
MP 0 to 6.3
I-294
24-Apr-15
Note - A after the above dates notes the ACTUAL DATE of the event.
Note - P after the above dates notes PENDING.
Page 2 of 2
Report Run: 1/30/2015